Mining Timeline
Building a Better World in Mining
With seven decades of global mining experience, Fluor has a record of success with complex projects in remote environments.
Fluor has the expertise to safely deliver new mining capacity, improve existing mine operational efficiencies and train local resources for long-term sustainability.
1950s
Fluor enters the Mining industry.
1956
Civil, mechanical and electrical works updated for Mount Isa Mines

1956: Civil, mechanical and electrical works updated for Mount Isa Mines

Civil and industrial projects undertaken in the 1950s were forerunners of Fluor’s later ventures in Australia’s mining industry. The 1956 Mount Isa project in northwest Queensland’s copper, lead, silver and zinc province was a significant expansion of the existing mines. The project was completed by Utah, which was later acquired by Fluor.
1960s
Fluor acquires Utah Construction and significant mining experience.
1965
First delivery of iron ore made to Finucane Island via 130-km rail from Mount Goldsworthy to Port Hedland

1965: First delivery of iron ore made to Finucane Island via 130-km rail from Mount Goldsworthy to Port Hedland

The Mount Goldsworthy Mining Associates consortium designed and built crushing, stockpiling, reclamation and rail loading facilities for Goldsworthy Mining Limited, Western Australia, in the first of an ongoing series of iron ore handling, railway and shipping projects involving Fluor in mining infrastructure throughout the Pilbara region. A 130-kilometer standard gauge railway was built to transport the iron ore from Mount Goldsworthy to Port Hedland.
1969
Fluor forms mining subsidiary with acquisition
&w=3840&q=75)
1969: Fluor forms mining subsidiary with acquisition
&w=3840&q=75)
Fluor Corporation acquires Utah Construction's engineering and construction division, augmenting Fluor's Mining and Metals division.
Fluor is a recognized leader in developing large, remote and technically complex mines and supporting facilities and infrastructure around the world.
1969
Fluor employs latest mining techniques in Nevada

1969: Fluor employs latest mining techniques in Nevada

Fluor used advanced techniques for mechanical tunneling on the River Mountain Project, a four-mile conduit connecting Lake Mead, Nevada with the Las Vegas Valley. The concrete-lined tunnel accommodated up to 132,000-acre feet of water a year - a boon for the high desert communities the Southern Nevada Water project served.
1969
Utah International's Shirley Basin Uranium Mill operational

1969: Utah International's Shirley Basin Uranium Mill operational

Utah International awarded Fluor the engineering, procurement and construction contract for the Shirley Basin Mill, a second-generation uranium plant. The new plant was the most advanced mill of its kind at the time. The compact design, placing most of the processing units within one area, incorporated many features used for the first time in the uranium processing industry.
The yellowcake shipped in 50-gallon drums to the customer where it was further processed to form the fuel for nuclear reactors.
1970s
Fluor's presence in the Mining industry expands globally in Australia and South America.
1970
Fluor constructs the Goonyella Coal Mine
&w=3840&q=75)
1970: Fluor constructs the Goonyella Coal Mine
&w=3840&q=75)
Fluor provided design and construction services on the Goonyella-Hay Point Coal Processing Facility and Port. This project was the second major coal project completed by Fluor in Queensland, Australia.
In addition to completing the coal processing facility and the port for the Goonyella Mine, Fluor also built the 140-mile railway linking Goonyella with Hay Point. Fluor provided these services to Queensland Government Railways as a separate contract.
1971
Fluor constructs Island Copper Complex for Utah International
&w=3840&q=75)
1971: Fluor constructs Island Copper Complex for Utah International
&w=3840&q=75)
The Island Copper Mine was located on the northern end of Vancouver Island about seven miles south of Port Hardy, in a remote logging and fishing community with a population of 2,000.
Fluor built the Island Copper Complex in 1971. The concentrator had a capacity to process 33,000 tons of ore per day. At the time, Island Copper's six autogenous grinding mills comprised the largest totally autogenous grinding circuit in the copper industry.
1971
Fluor mobilizes to construct a grassroots uranium processing facility at Rabbit Lake

1971: Fluor mobilizes to construct a grassroots uranium processing facility at Rabbit Lake

Fluor’s scope of work included a 28,000-square meter main complex that housed the process units, acid plant, power plant, laboratory, offices, workshop and warehouses.
Located 800 kilometers northwest of Saskatoon, Rabbit Lake was a very challenging project to execute in extreme environmental conditions. In spite of the challenges and only short periods of summer construction, the project was completed on schedule in April 1975.
1972
Pima capacity boosted to 53,500 tons of copper/molybdenum ore daily

1972: Pima capacity boosted to 53,500 tons of copper/molybdenum ore daily

The Pima IV project was completed in 1972. The expansion of the Pima Mining Company's complex, near Tucson, Arizona, increased the mine's capacity from 39,500 to 53,500 tons of copper/molybdenum ore per day.
Fluor added new crushing, stockpiling and flotation facilities. Additionally, Fluor installed the largest radial stacking conveyor in the world at 256 feet long with a capacity of 3,200 tons per hour. The project was the fourth expansion since 1955, when Utah Construction built the original mill.
1973
Rosario Dominicana, S.A. Gold and Silver Ore Processing Facility project awarded

1973: Rosario Dominicana, S.A. Gold and Silver Ore Processing Facility project awarded

Fluor provided engineering and procurement for this 8,000 tpd gold and silver ore processing facility. The plant uses semi-autogenous grinding, sodium-cyanide leaching and fire refining unit processes.
1973
L-Bar Uranium Mine and Mill EPC work begins for Sohio and Reserve

1973: L-Bar Uranium Mine and Mill EPC work begins for Sohio and Reserve

Fluor was selected by Sohio and Reserve because of its extensive experience in second generation uranium processing mills. Fluor performed the early feasibility studies and ultimately took overall responsibility for engineering, procurement, and construction of the L-Bar underground mine, laboratory and mill complex, which includes semi-autogenous grinding, acid leaching and counter-current washing.
1973
Fluor designs and constructs secondary crushing and screening plant for Hamersley Iron Ore

1973: Fluor designs and constructs secondary crushing and screening plant for Hamersley Iron Ore

Fluor designed and constructed the secondary crushing and screening plant at Paraburdoo for Hamersley Iron Ore. The iron ore was hauled by trucks from the mine to the primary crusher and belt-conveyed to stockpile for secondary crushing.
1976
Copper ore moves from Cuajone to Ilo

1976: Copper ore moves from Cuajone to Ilo

Fluor managed the construction of Southern Peru Copper Corporation's mining and ore-processing project at Cuajone. At an elevation of 11,600 feet, the Cuajone mine is located 1,400 kilometers southeast of Lima. The project, which began in 1971 with preliminary design was concluded in mid-1976.
1977
Cordero Coal Mine begins operations in Gillette, Wyoming

1977: Cordero Coal Mine begins operations in Gillette, Wyoming

The project began with a Fluor feasibility study of the 6,540-acre federal lease. It proceeded through engineering, procurement and construction management for the entire coal mine, handling, preparation and shipping facilities. The processing and loading facilities were designed to handle 12 million tons of coal per year with provision for later expansion to the present 24 million tons.
Fluor successfully completed the Cordero Mine project ahead of schedule and under budget.
1977
Cyprus Bagdad Copper Expansion project completed
&w=3840&q=75)
1977: Cyprus Bagdad Copper Expansion project completed
&w=3840&q=75)
The Cyprus Bagdad Copper Company selected Fluor, in a joint venture with Holmes and Narver, for the engineering, procurement, and construction of expanded copper concentrating facilities at the Cyprus Bagdad Copper Company operation in western Arizona. The $240 million expansion project boosted mine production from 6,000 tons of copper ore a day, to 40,000 tons daily, a 700 percent increase in the mine’s capacity.
1977
U.S. Steel/Niagara Mohawk's Clay West Uranium Plant operational

1977: U.S. Steel/Niagara Mohawk's Clay West Uranium Plant operational

The Clay West Plant was designed to produce a 2,200 pound /day of U3O8 yellow cake.
The Clay West Plant was a large-scale plant using in-situ carbonate leach process. The ammonium carbonate solutions were injected into the ore body, and the pregnant uranium solutions were pumped out through a series of wells. Fluor designed both the well gathering systems and the porter resin ion exchange process units. Loaded resin was trucked to the elution facility.
1979
Codelco's Chuquicamata copper ore concentrator expanded
&w=3840&q=75)
1979: Codelco's Chuquicamata copper ore concentrator expanded
&w=3840&q=75)
Fluor provided the engineering and procurement services for the expansion of Codelco's Chuquicamata copper ore concentrator. This project expanded the Chuquicamata concentrator from 74,000 to 96,000 mtpd. Facilities included fine ore bins, rod and ball mill circuit, flotation and tailing thickening.
During the course of the project, Fluor prepared detailed specifications and conducted evaluation and selection of the world's first semi-autogenous grinding (SAG) mills driven by 10,000 HP wrap-around motors. The two SAG mills were capable of grinding 50,000 metric tons of copper-bearing ore per day.
1979
Sasol Coal-to-Gas Project in South Africa completed
&w=3840&q=75)
1979: Sasol Coal-to-Gas Project in South Africa completed
&w=3840&q=75)
Fluor constructs the first large-scale commercial liquid fuels-from-coal plant known as Sasol II in Secunda, South Africa, eliminating South Africa's dependency on imported gas. Sasol processes sub-bituminous coal into gasoline, diesel, jet fuels, ethylene, ammonia, sulfur and various chemicals and coal tar products.
1980s
Fluor adds significant Mining expertise with Canadian acquisition.
1981
Coal Creek’s grassroots coal mine production starts up

1981: Coal Creek’s grassroots coal mine production starts up

Fluor performed engineering, procurement, construction and start-up assistance on the Coal Creek Mine. The mine was comprised of coal processing, storage, loadout and ancillary facilities for producing 12 million tons per year of low-sulfur coal. Plant design called for sufficient output to load unit trains on a seven-day-per-week schedule at a rate of 10,000 tons per hour. Coal Creek was a grassroots plant requiring complete and integrated facilities with the ability to receive, process and ship coal.
1981
El Indio's remote gold, silver and copper mine processing commences

1981: El Indio's remote gold, silver and copper mine processing commences

Fluor provided engineering, procurement, construction management and start-up services to Compañía Minera El Indio for gold, silver and copper processing facilities at a site 14,000 feet up in the Chilean Andes.
1983
Fluor provides construction management services for MIM Holdings Ltd.'s Abbot Point Coal Mine

1983: Fluor provides construction management services for MIM Holdings Ltd.'s Abbot Point Coal Mine

Fluor provides construction management services for MIM Holdings Ltd.'s Abbot Point Coal Mine. At construction, the mine was one of Australia's largest deep water coal shipping ports.
1983
Fluor completes largest industrial coal to liquids facility in the world for Sasol

1983: Fluor completes largest industrial coal to liquids facility in the world for Sasol

Fluor completed the construction of the Sasol II and III in Secunda, South Africa. Sasol processes sub-bituminous coal into gasoline, diesel, jet fuel, ethylene, ammonia, sulfur and various chemicals and coal tar products.
1983
Fushun coal production modernization study delivered
&w=3840&q=75)
1983: Fushun coal production modernization study delivered
&w=3840&q=75)
Fluor completed the feasibility study, basic engineering and consulting services for the modernization and expansion of the oil shale open-cut coal production facility at the Fushun Mine. The mine was first opened in the early 1900s and at the time was the largest in China.
1986
Minera Escondida Copper Mine project begins
&w=3840&q=75)
1986: Minera Escondida Copper Mine project begins
&w=3840&q=75)
Fluor designs and constructs the Minera Escondida project – one of the world’s largest copper mines – located in the Atacama Desert of Chile, which is the driest place on earth.
1987
Engineering underway for Codelco's El Teniente expansion

1987: Engineering underway for Codelco's El Teniente expansion

Fluor engineered an expansion to the El Teniente SAG Mill Expansion. The engineering encompassed an addition of a 25,000 tpd module to the Colon concentrator.
1988
Fluor acquires Wright Engineers Limited in Vancouver

1988: Fluor acquires Wright Engineers Limited in Vancouver

Fluor's acquisition of Wright Engineers Limited added significant mining and metals expertise to Fluor in Canada. To date, Fluor continues to maintain an office in Vancouver to provide engineering support for mining and metals projects around the globe.
1988
Fluor awarded detailed design for Colomac's Gold Processing Mine

1988: Fluor awarded detailed design for Colomac's Gold Processing Mine

Fluor provided detailed design, procurement, construction management and start-up services for all the process facilities at Colomac's 10,000 tpd gold processing facilities. The remote location and the severe climate of Canada's Northwest Territories offered many challenges. Despite those challenges, Fluor completed the project on time and within budget.
1988
First commercial use of an oxygen scrub/recycle system at gold ore treatment plant

1988: First commercial use of an oxygen scrub/recycle system at gold ore treatment plant

Fluor performed an engineering study aimed at optimizing a plant expansion to this 3,000 tpd refractory gold ore treatment plant following the discovery of a new gold ore body adjacent to the mine.
Fluor provided process design, a feasibility study, detailed design, procurement and construction management assistance for the leaching refractory gold ore in pressure oxidation autoclaves. These autoclaves were installed and this was the first commercial use of oxygen scrub/recycle system.
1989
Hilton Lead-Zinc Mine Expansion was one of a number of projects completed for Mount Isa Mines
&w=3840&q=75)
1989: Hilton Lead-Zinc Mine Expansion was one of a number of projects completed for Mount Isa Mines
&w=3840&q=75)
In 1989, Fluor expanded the Hilton mine with a new lead-zinc concentrator.
1989
Bullfrog Gold Project concludes in Beatty, Nevada

1989: Bullfrog Gold Project concludes in Beatty, Nevada

Fluor performed engineering, procurement, construction management and start-up services for Dallhold Resources' Bullfrog Gold Project in Beatty, Nevada. The mine is an 8,220-tpd open-pit gold mine. The orebody is mined for gold and silver.
1989
Highland Valley Copper expansions online

1989: Highland Valley Copper expansions online

The Highland Valley Copper mine provided copper ore to the Lornex concentrator. Fluor engineered and managed construction for the two in-pit 60/89 movable crushing stations and the overland conveyor transportation systems from the pit to the concentrator. The concentrator was expanded by the addition of the two Highmont SAG mills, a Highmont stacker and a new coarse ore stockpile.
1990s
Fluor receives recognition for Mining projects.
1991
Expanded Freeport Indonesia Copper/Gold Mine completed
&w=3840&q=75)
1991: Expanded Freeport Indonesia Copper/Gold Mine completed
&w=3840&q=75)
Fluor performed detailed engineering, procurement and construction services for the expansion of the copper/gold mining complex. The expansion involved three-stage crushing, grinding, rougher and cleaner flotation, regrinding, concentrate and tailing thickening, concentrate slurry pipeline, filtering and loadout.
1992
Marillana Creek Mine at Yandicoogina wins Western Australia Engineering Award
&w=3840&q=75)
1992: Marillana Creek Mine at Yandicoogina wins Western Australia Engineering Award
&w=3840&q=75)
Fluor was awarded a contract by BHP Iron Ore Ltd. to perform engineering, procurement and construction management of the Marillana Creek Mine facilities including a stacker, loadout tunnel and 32 km of new, heavy-haul railway to link to BHP’s existing rail system
The project took just 10 months from earthworks to production and earned BHP Iron Ore the Institution of Engineers Western Australia Award for outstanding engineering achievement in the Resource Development Category. The Marillana Project was one of two major developments of the high-purity iron ore deposit at Yandicoogina.
1994
Nickel underground mine re-opens in Garson, Ontario
&w=3840&q=75)
1994: Nickel underground mine re-opens in Garson, Ontario
&w=3840&q=75)
The Garson Mine operated for almost 50 years before it was closed in 1987. In 1992, INCO commissioned a study to re-open the mine. Fluor provided engineering, procurement and construction management services for the 2,000 tpd nickel underground mine in Garson, Ontario. Fluor renovated existing facilities as well as constructed new facilities.
1994
Two stage expansion of the Escondida mine raises the mine and concentrator capacity to 60,000 tpd

1994: Two stage expansion of the Escondida mine raises the mine and concentrator capacity to 60,000 tpd

Minera Escondida Ltda. operates the Escondida mine and copper concentrator located in the Atacama desert 160 km. southeast of the port of Antofagasta in northern Chile and the concentrate dewatering and ship-loading facilities at their port in Coloso, south of Antofagasta. Fluor completed the original grass roots Los Colorados copper concentrator project and subsequently provided a full range of services on expansion projects at the site. Phase I and II expansions raised the mine and concentrator capacity to 60,000 tpd by the end of 1994.
1994
Compania Minera's Quebrada Blanca 75,000 tpy copper mine on line

1994: Compania Minera's Quebrada Blanca 75,000 tpy copper mine on line

Fluor provided EPCM services for this copper leach/SX-EW facility on a brownfield site, at 4,400 meter msl elevation. The project included primary crushing, secondary/tertiary crushing, agglomeration, heap stacking, thin layer leaching, SX system, EW tank house, powerhouse, 138-km access road, water well field, 35-km water pipeline, shops, offices, and camp. Copper is recovered from the leaching solutions in three parallel SX trains, designed to process a nominal 2,769 cubic meters per hour of PLS. The EW plant is designed to produce a nominal 216 tons per day or 75,000 tons per year of high grade copper cathodes. A fully automated cathode washing and stripping machine is incorporated to process 360 cathodes per hour to harvest the copper.
1995
Fluor awarded Perú’s first large-scale heap-leaching project by Minera Yanacocha S.R.L.

1995: Fluor awarded Perú’s first large-scale heap-leaching project by Minera Yanacocha S.R.L.

Minera Yanacocha S.R.L. (MYSRL) was the largest gold producer in Latin America and represented Perú’s first large-scale heap-leaching operation in 1995. MYSRL consisted of several mine pits, gold recovery plants and leach pads. As part of a global alliance with Newmont, Fluor provided engineering, procurement, construction and maintenance services for a series of expansions, upgrades and maintenance at Yanacocha.
1995
Sasol Twistdraai Coal Washing Plant awarded
1995: Sasol Twistdraai Coal Washing Plant awarded
Sasol awarded Fluor the engineering and construction of the Sasol Twistdraai Coal Washing Plant near Secunda. The washing plant included a 1430 tph cyclone module (3 off) with fine coal spirals, 80-mm diameter dense medium cyclones, 2-cyclone module treating 800 tph and filter press plant.
1995
Bing Bong Port Project awarded the Northern Territory Earth Award

1995: Bing Bong Port Project awarded the Northern Territory Earth Award

Fluor provided engineering, procurement and construction management for the McArthur River mine, Bing Bong port and ship-loading facilities. A 60-meter wide, four-kilometer channel was dredged to barge the concentrate from the port to the bulk carrier. The project was handed over to the client two months ahead of schedule and five per cent less than the approved budget. The Bing Bong Port project was awarded the Northern Territory Earth Award.
1995
Placer Dome's Zaldivar Heap Leach SX-EW project engineered
&w=3840&q=75)
1995: Placer Dome's Zaldivar Heap Leach SX-EW project engineered
&w=3840&q=75)
As part of Placer Dome's Zaldivar Heap Leach SX-EW project, Fluor engineered a heap leaching and SX-EW facility producing 125,000 tons of cathode copper per year. We also engineered the heap leach stacking system. The engineering work was executed from Fluor's Vancouver office.
1996
WMC announces plans to increase refined copper output at Olympic Dam
&w=3840&q=75)
1996: WMC announces plans to increase refined copper output at Olympic Dam
&w=3840&q=75)
For Fluor, this was an encore engagement. It had already worked with WMC at Olympic Dam, providing the original project’s feasibility study, engineering, procurement and construction management for the hydrometallurgical plant, copper smelter and refinery, and the procurement and construction management for all surface processing facilities. Fluor also provided technical input to the concentrator and smelter design, as well as procurement and construction management for all metallurgical plants.
1996
Phase III Expansion at Escondida increases copper concentrator capacity to 115,000 tpd

1996: Phase III Expansion at Escondida increases copper concentrator capacity to 115,000 tpd

Phase III of the Escondida expansion increased the concentrator's capacity to 115,000 tpd. The scope included in-pit crushing, conveying, grinding, flotation, tailings disposal, process water, a new 165-km pipeline, and an expansion to the filter plant at the port site.
1997
Nickel and cobalt from laterite ores recovered at Anaconda Limited's Murrin Murrin mine
&w=3840&q=75)
1997: Nickel and cobalt from laterite ores recovered at Anaconda Limited's Murrin Murrin mine
&w=3840&q=75)
The Murrin Murrin project called for ore processing rates of almost four million tonnes per annum to produce 45,000 tonnes of high purity nickel and 3,000 tonnes of high purity cobalt, per year. Fluor developed an aggressive schedule that began in January 1997 and had pre-commissioning completed in 22 months. The big challenge was extracting nickel from laterite ore, rather than from the traditional sulphide ore smelting. The new process called for high-pressure acid leaching in four gigantic titanium lined autoclaves.
1997
BHP Cannington Silver/Lead Mine commissioned

1997: BHP Cannington Silver/Lead Mine commissioned

A Fluor subsidiary worked on design and procurement of equipment for primary crushing, autogenous grinding, differential flotation and tailings disposal, together with the regrind, leaching, dewatering, handling and transport of concentrates. Transports were by road train to a rail loading facility at Yurbi, about 15 kilometers east of Cloncurry, and by rail to a modern mineral concentrate handling facility at Townsville.
1998
Fluor completes Cuajone Copper Mine Expansion

1998: Fluor completes Cuajone Copper Mine Expansion

The Cuajone Mine, located in the rugged Peruvian Andes at 12,000 feet, was the largest single copper mine and smelter complex ever built.
Fluor performed detailed engineering, procurement and construction management services along with training for 7,000 local workers at peak.
1998
Copper concentrator, 125,000 tpy oxide leach/SX-EW plant at Minera Escondida complete

1998: Copper concentrator, 125,000 tpy oxide leach/SX-EW plant at Minera Escondida complete

Fluor provided feasibility study and complete EPCM services for a 125,000 tpy oxide leach/SX–EW facility, including a 54,000 tpd crushing and screening plant, materials handling, heap leaching and ancillaries. Project completed ahead of schedule and under budget in 1998.
1998
Fluor completes Ernest Henry Copper/Gold Mine and Processing Plant three months ahead of schedule
&w=3840&q=75)
1998: Fluor completes Ernest Henry Copper/Gold Mine and Processing Plant three months ahead of schedule
&w=3840&q=75)
The first truckload of copper concentrate rolled out of the Ernest Henry Copper Mine, 38 kilometers northeast of Cloncurry in central Queensland three months ahead of schedule. Ernest Henry Mining’s development team and Fluor brought the project to production in 21 months, yielding better production rates than the design had anticipated, making it Australia’s third most productive copper mine at the time.
Fluor prepared the feasibility study and built the greenfield gold/copper mine and its infrastructure, including a 115-kilometer water supply pipeline and an all-weather road between Cloncurry and the mine.
1998
Lomas Bayas SX-EW plant constructed
&w=3840&q=75)
1998: Lomas Bayas SX-EW plant constructed
&w=3840&q=75)
Fluor provided self-perform engineering and construction services on a lump sum basis for this low-cost, 60,000 tpy greenfield copper SX-EW facility in northern Chile. Facilities include ore crushing and conveying, tub heap leach pad, SX-EW plant, administration building, maintenance, 220 kV substation, permanent camp, 140 km water supply pipeline, and water treatment plant.
The SX-EW facility consisted of a single train solvent extraction circuit and a 180 cell electrowinning tankhouse. A Kidd Technology automated stripping machine was provided to strip 250 cathodes per hour. The power supply is received from the utility company at 220 kV in the main substation, where two main step-down transformers distribute power at 6.6 kV throughout the plant.
1999
Palabora Underground Mine expanded
&w=3840&q=75)
1999: Palabora Underground Mine expanded
&w=3840&q=75)
Fluor provided engineering, procurement and construction management for the 60,000 tpd underground copper mine and modifications to existing metallurgical plant.
1999
Copper concentrator capacity at Escondida increased to 132,000 tpd

1999: Copper concentrator capacity at Escondida increased to 132,000 tpd

In 1999, Fluor completed the Phase 3.5 expansion of Escondida. The expansion increased the mine and concentrator capacity to 132,000 tpd.
2000s
Fluor achieves major Mining milestones in Australia and South Africa.
2000
Production begins at MIM Enterprise Copper Mine
&w=3840&q=75)
2000: Production begins at MIM Enterprise Copper Mine
&w=3840&q=75)
MIM decided to develop its Enterprise Copper Mine deep under its existing operations. Careful planning was vital to minimize disruption to ore production and haulage.
At the time, this would be Australia’s deepest mine. Fluor provided engineering, procurement and construction management to access the ore by sinking an internal shaft that connected with an existing shaft, which then reached 1,900 meters into the earth. Additionally, Fluor designed the backfill plant at Enterprise.
2001
Fluor completes De Beers' CTP project in Kimberley
2001: Fluor completes De Beers' CTP project in Kimberley
Fluor successfully completed the CTP Project, a diamond processing facility for De Beers in Kimberley. The plant was designed to treat several old tailings dumps for the recovery of diamonds located in the area. The plant was designed to be able to handle a wide range of ore characteristics. The fine tailings disposal is achieved by pumping high density slurry a distance of 5 km, using the largest available positive displacement pumps, in only the second installation of its type in South Africa.
2001
Fluor-led Mine & Port Development JV selected for BHP Billiton's multi-billion dollar expansion
&w=3840&q=75)
2001: Fluor-led Mine & Port Development JV selected for BHP Billiton's multi-billion dollar expansion
&w=3840&q=75)
BHP Billiton’s Iron Ore Expansion Programme was implemented in 2001 to increase their iron ore capacity and operations in the region. Market factors driving the programme included: ‘Speed to market’ to capitalise on the high iron ore demand driven primarily by China; deliver an expansion ‘programme’ rather than a series of stand-alone projects; and the need for a dependable EPCM service provider during the boom times of the Western Australia economy. A series of projects followed over the next 14 years.
2001
Fluor successfully completes EPC services at Batu Hijau, a 120,000 tpd copper/gold mine
&w=3840&q=75)
2001: Fluor successfully completes EPC services at Batu Hijau, a 120,000 tpd copper/gold mine
&w=3840&q=75)
Fluor performed engineering, procurement, and construction on the world’s largest greenfield mining project at the time on the remote island of Sumbawa in Indonesia with no infrastructure, a sparse and unskilled workforce, amid economic and political turmoil. Fluor completed engineering in 1996, and completed construction in 2001.
2002
Phase IV Expansion at Escondida commissioned
2002: Phase IV Expansion at Escondida commissioned
The Phase IV Expansion at the Minera Escondida Copper Mine increased the mine and mill capacity from 132,000 tpd to 253,000 tpd. Additionally the Laguna Seca concentrator was added as part of this expansion.
2002
Production begins at Albian Sands Muskeg Oil Sands Mine

2002: Production begins at Albian Sands Muskeg Oil Sands Mine

Fluor performed EPC and maintenance for the Muskeg River Oil Sands Mine constructed as part of the Athabasca Oil Sands project. The project was designed to produce 155,000 barrels per day of bitumen.
2002
Bwana Mkubwa facility completed in Zambia

2002: Bwana Mkubwa facility completed in Zambia

Bwana Mkubwa was one of the world’s lowest-cost copper operations. The two-phase expansion included conversion from a tailings leach to an ore tank leach operation. Fluor provided fast-track services for engineering, procurement, construction support and commissioning of the project.
2002
South Africa's largest grassroots gold mine built for Avgold in Free State

2002: South Africa's largest grassroots gold mine built for Avgold in Free State

Fluor performed detailed design of the processes, structures and mechanical and electrical works, as well as construction of Avgold's Target Gold Mine Processing Plant. The facility, completed in 2002, was the first large grassroots gold mine built in South Africa in 20 years.
2004
Fluor recognized for WAIO Programme efforts

2004: Fluor recognized for WAIO Programme efforts

The Fluor-led joint venture, MPD JV, was engaged by BHPBIO to assist in the execution of its iron ore expansion projects to increase mining, processing, rail transportation, stockpiling and shiploading capabilities across BHP Billiton’s Pilbara iron ore assets.
The Programme received numerous awards, including:
Institute of Engineers Australia National Award 2004 (Rail Project)
Railway Technical Society of Australasia (RTSA) Biennial Industry Award 2004
WA Engineering Excellence Awards 2004 (Rail and Mine/Port Projects)
2005
Kansanshi Copper Oxide Ore Circuit Upgrade commissioned

2005: Kansanshi Copper Oxide Ore Circuit Upgrade commissioned

Fluor’s scope of work was to provide engineering and design services to support procurement and construction of plant equipment for treating the targeted 12 million tpa of sulphide ore. The scope also included (for the oxide plant) two countercurrent decantation thickeners and a new gravity concentrator. Engineering services comprised civil, structural, architectural, mechanical and piping design.
2006
Mine & Port Development JV completes BHP Billiton's Rapid Growth Project 2 (RGP2)
&w=3840&q=75)
2006: Mine & Port Development JV completes BHP Billiton's Rapid Growth Project 2 (RGP2)
&w=3840&q=75)
The RGP2 project, part of BHP Billiton's Western Australia Iron Ore Growth Programme, included the development of a new mine at Orebody 18, comprising an ore handling plant and non-process infrastructure and services. Additionally, the JV modified the Orebody 24 mine to produce lump and fine products, constructed a new car dumper at the port and built additional rail to support the new Orebody 18 mine and car dumper.
2006
Fluor delivers EPCM services for Escondida's Sulphide Leach Project
&w=3840&q=75)
2006: Fluor delivers EPCM services for Escondida's Sulphide Leach Project
&w=3840&q=75)
The project involved heap leaching, a two-train SW plant, EW tank house, and mine infrastructure. The installed capacity of the plant is 200,000 tpy of cathode copper. As part of the Sulphide Leach Project, Escondida pioneered the use of desalination for process water in this arid region of Chile. Water supply originates from the 500-litre-per-second desalination plant constructed by Fluor. Water is pumped through a 24-inch, 167-kilometer pipeline with four intermediate 12,000-horsepower pumping stations on the route from sea level at the port to an altitude of 3,200 meters at the mine site. During construction of Sulphide Leach, the project achieved 7 million hours without an OSHA lost-time incident – a Chilean record.
2007
Cerro Verde Primary Sulfide Project processing facilities operational

2007: Cerro Verde Primary Sulfide Project processing facilities operational

The Cerro Verde Primary Sulfide Project was an expansion of existing processing facilities that extract copper from oxide copper ore using conventional heap leach and SX/EW technology. The concentrator processes sulfide copper ore from existing mining pits approximately tripling annual production at the site from 100,000 tonnes of copper to 300,000 tonnes.
2008
Chilean President Michelle Bachelet inaugurates Codelco's Gaby copper mine

2008: Chilean President Michelle Bachelet inaugurates Codelco's Gaby copper mine

Fluor performed engineering, procurement, construction management and precommissioning of the $980 million project for Codelco, the world's largest producer of copper. The project demonstrated the efficacy of Codelco's joint team approach.
It was completed within budget and in 22 months – considered an industry record for engineering, procurement and construction management of a major SX/EW plant.
2008
Oz Minerals' Prominent Hill Copper/Gold Project operational
&w=3840&q=75)
2008: Oz Minerals' Prominent Hill Copper/Gold Project operational
&w=3840&q=75)
Fluor completed the USD $700 million Prominent Hill Copper/Gold Project for OZ Minerals, the first major mining project in the region since an expansion of the Olympic Dam in the 1990s, which also involved Fluor.
2008
FAST JV develops new mine at E Deposit and completes expansion work
2008: FAST JV develops new mine at E Deposit and completes expansion work
The newly renamed JV between Fluor and SKM, FAST JV, continued development and construction for BHP Billiton in Pilbara. The RPG3 project was completed in 2008 and included development of a new mine at ‘E Deposit’, construction of a new overland conveyor from E Deposit to Area C and new crushing and screening facilities and second blending yard at Area C. Additional upgrades were made at Nelson Point and Berth C at Finucane Island, and rail expansion work included new rail mainline, spur sidings and loop modifications at Area C.
2009
Rio Tinto awards Fluor with the 2009 Safety Award
&w=3840&q=75)
2009: Rio Tinto awards Fluor with the 2009 Safety Award
&w=3840&q=75)
The QMM Mineral Sands Project was recognised by Rio Tinto's Chief Executive with the 2009 Safety Award for outstanding safety performance. Fluor achieved 12 million consecutive safe workhours without a lost-time incident, a record in Madagascar and one of the top performances for a Rio Tinto project. The award also recognised our efforts to build a sustaining safety culture for the community and country.
2010s
Fluor employs innovative Mining techniques around the globe.
2010
FAST JV achieves additional project milestones for BHP Billiton in Pilbara region

2010: FAST JV achieves additional project milestones for BHP Billiton in Pilbara region

RPG4 milestones included a new ore processing plant at Jimblebar, ore handling upgrades at Yandi and a new crushing and screening plant, additional stockyards, car dumping and train loading facilities at Mt. Whaleback. Additionally, the FAST JV expanded the port at Nelson Point, upgraded the stockyard and constructed new offices, warehouse and workshops at Finucane Island, all part of BHP Billiton’s Growth Programme.
2010
ICA Fluor completes EPCM work for Boleo Copper Mine Development
2010: ICA Fluor completes EPCM work for Boleo Copper Mine Development
ICA Fluor, Fluor’s joint venture company in Mexico, was awarded preliminary and full engineering, procurement and construction management for the Boleo mining project near the town of Santa Rosalia, located in Baja California Sur, Mexico.
The project is an underground and surface mining operation providing run-of-mine ore to a fully integrated hydrometallurgical facility.
2011
Fluor achieves first coal milestone at Debswana Mining Morupule Colliery Expansion
2011: Fluor achieves first coal milestone at Debswana Mining Morupule Colliery Expansion
Fluor performed engineering, procurement and construction management for the project. The main target was to complete the relevant facilities to support meeting the “first coal” milestone. Fluor achieved this significant milestone two weeks ahead of schedule. This milestone was preceded by an intricate shutdown to dismantle existing facilities, and tie-in, test and commission the required new process facilities and systems to enable coal to be conveyed to Morupule ‘B’ power station. All new facilities were built around the existing plant while it was still producing coal for the Morupule ‘A’ power station and other clients.
2011
KGHM International Ltd. Sierra Gorda Copper-Molybdenum Mine awarded to Fluor
&w=3840&q=75)
2011: KGHM International Ltd. Sierra Gorda Copper-Molybdenum Mine awarded to Fluor
&w=3840&q=75)
Fluor performed the feasibility study and engineering, procurement and construction management services for the Sierra Gorda Mine Processing Plant.
The processing plant consists of: primary, secondary and tertiary crushing with high-pressure grinding rolls; ball milling and conventional flotation to produce a bulk copper-molybdenum concentrate; train transport of bulk copper concentrate to the Port of Mejillones for loading into ships; and train transport of bagged molybdenum concentrate to the port for further transport to a toll roasting facility or end user.
2011
FAST JV completes Rapid Growth Project 5 on schedule

2011: FAST JV completes Rapid Growth Project 5 on schedule

BHP Billiton’s RPG5 was completed on schedule in 2011. The project included expanding the Yandi Mining Hub, including the construction of a new 45-Mtpa ore handling plant (OHP3) and tie-in to the existing OHP2, plus the construction of supporting non-process infrastructure. Significant completions also included the port expansion with the construction of two new berths and two new shiploaders at Finucane Island, plus car dumper modifications and conveyor route upgrades and rail development including extensive upgrades to a dual rail track system.
2012
Construction concludes at Pueblo Viejo Gold/Silver Mine

2012: Construction concludes at Pueblo Viejo Gold/Silver Mine

Fluor successfully completed the feasibility study and provided engineering, procurement and construction management services for the $3.8 billion Pueblo Viejo Project, the largest foreign investment in the history of the Dominican Republic.
At peak construction, the project had a workforce of 7,800 comprised of 17 nationalities interacting and working together.
2012
Jwaneng Diamond Mine completed

2012: Jwaneng Diamond Mine completed

The Jwaneng Open Pit Diamond Mine is the largest, by value, in the world. Its expansion facilitates greater access to kimberlite ore. Fluor performed engineering, procurement and construction management services for associated relocation and rebuilding of the mine surface infrastructure. The project was completed in September 2012.
2012
Fluor completes scope at Newcrest Mining's Cadia East Gold/Copper Mine

2012: Fluor completes scope at Newcrest Mining's Cadia East Gold/Copper Mine

Cadia East was Australia's first panel-cave mine and is Australia's largest underground mine. Fluor was the procurement and construction manager for the surface process plant and underground material handling, as well as, engineering, procurement and construction management for surface and underground infrastructure.
2013
FAST JV constructs Orebody 24 Mine for BHP Billiton

2013: FAST JV constructs Orebody 24 Mine for BHP Billiton

The Orebody 24 project was part of the overall BHPBIO programme in Western Australia. In 2013, the Fluor-led, FAST JV constructed the Orebody 24 mine ore handling plant, non-process infrastructure and services to replace the Jimblebar Wheelarra 4 primary crushed ore supply to Newman Hub (14 Mtpa).
2013
Caserones 110,000 tonnes per day Cu Concentrator completed
&w=3840&q=75)
2013: Caserones 110,000 tonnes per day Cu Concentrator completed
&w=3840&q=75)
Fluor performed engineering, procurement and construction management services for facilities, utilities and offsites and mine-related infrastructure at the Caserones Copper Project in Chile. The Caserones Mine produces copper concentrate, copper cathodes and molybdenum concentrate from an open mine operation.
2013
Oyu Tolgoi Copper Mine operations commence

2013: Oyu Tolgoi Copper Mine operations commence

In the arid, very remote Gobi Desert in Mongolia, Fluor provided program and construction management to Ivanhoe Mines Ltd. on their $6 billion Oyu Tolgoi copper mine.
This mine represented the largest and perhaps most challenging engineering-construction project in Mongolia, and became one of the world’s largest copper mines when it commenced operations in 2013.
2014
Surface mining and bitumen extraction operational at Kearl Oil Sands in Alberta

2014: Surface mining and bitumen extraction operational at Kearl Oil Sands in Alberta

The Kearl Initial Development surface mining and bitumen extraction operation will achieve a total production of 110,000 barrels per day (bpd). The Kearl Expansion Project operation is expected to add a total production of 110,000 bpd. Imperial has a mine plan for the project life of over 40 years, and production capacity is an approved 345,000 bpd.
2014
Teck Highland Valley Copper Mill Optimization Project completed

2014: Teck Highland Valley Copper Mill Optimization Project completed

Fluor completed the pre-feasibility study for modernization of the Highland Valley Copper Mine concentrator and performed engineering, procurement and construction management services for this 125,000 tons per day open-pit copper-molybdenum mine.
2015
WAIO Growth Programme nearly triples BHP Billiton's Iron Ore production capacity

2015: WAIO Growth Programme nearly triples BHP Billiton's Iron Ore production capacity

The WAIO Growth Programme is a series of projects that increased BHPBIO’s production capacity over a nearly 15-year period through the completion of 10 major projects. The Fluor-led joint venture, FAST JV, successfully executed one of the world’s largest multi-billion dollar expansion programmes, with projects consistently delivered on schedule and on budget, and assisted BHP Billiton in strengthening its position as one of the world’s leading iron ore producers.
2015
Fluor opens in Botswana
&w=3840&q=75)
2015: Fluor opens in Botswana
&w=3840&q=75)
Fluor opened an office in Gaborone, Botswana in 2015. Fluor's previous experience in Botswana includes the Orapa Diamond Mine and the Jwaneng Cut 8 and Morupule Coal Mine Expansion Projects. The newly established office allows Fluor to continue offering integrated EPC solutions to Mining & Metals clients in Botswana.
2015
Quellaveco Open Pit Copper Mine under construction

2015: Quellaveco Open Pit Copper Mine under construction

Quellaveco is a typical porphyry copper deposit. The operation will use processing by flotation to produce copper concentrates and molybdenum. The project, located approximately 130 kilometers southeast of Arequipa, will exploit a significantly sized copper/molybdenum ore body at an altitude of around 3,500 meters. Fluor provided project planning and early engineering services from its offices in Lima, Perú and Santiago, Chile. Currently, Fluor is completing the feasibility study and leading construction management for early site works. The Anglo American Board will determine approval for a phased approach in late 2016.
2015
Fluor completes EPCM on Ma'aden Aluminum Automotive Sheet Facility
&w=3840&q=75)
2015: Fluor completes EPCM on Ma'aden Aluminum Automotive Sheet Facility
&w=3840&q=75)
The Saudi Arabian Mining Company (Ma’aden) and Alcoa formed a joint venture to execute several projects as part of the Ma’aden Aluminum project. Fluor provided project management consultant services for the overall program, as well as engineering, procurement and construction (EPC) for the bauxite mine and alumina refinery, basic engineering and engineering, procurement and construction management (EPCM) for the rolling mill and EPCM services for the automotive sheet facility.
2016
World's largest copper concentrator, part of the Production Unit Expansion at the Cerro Verde Mine
&w=3840&q=75)
2016: World's largest copper concentrator, part of the Production Unit Expansion at the Cerro Verde Mine
&w=3840&q=75)
The Cerro Verde Production Unit Expansion is considered not only world-class, but is also the largest one-time built copper concentrator on the planet. Fluor provided engineering, procurement, construction management (EPCM) and commissioning services for the new concentrator.
2017
Fluor applies modular approach to Letlhakane Mine project

2017: Fluor applies modular approach to Letlhakane Mine project

Fluor designed 60 process modules and 106 conveyor and services gantry modules for Debswana Diamond Company’s Letlhakane Mine Tailings Resource Treatment Project in Botswana. The project will extend the Letlhakane operation’s life-of-mine by 25 years.
2017
Ma’aden Umm Wu’al integrated phosphate fertilizer facility to be one of world’s largest

2017: Ma’aden Umm Wu’al integrated phosphate fertilizer facility to be one of world’s largest

Fluor is providing project management consulting services for Ma’aden Wa’ad Al Shamal Phosphate Company’s Umm Wu’al Phosphate Project and related facilities. The Umm Wu’al project will be one of the largest integrated phosphate fertilizer facilities in the world, with an annual capacity of 3 million MPTA of DAP/MAP and NPK fertilizers. The project is scheduled for completion in the summer of 2017.
2017
Fluor completes FEED scope for the Ona Mining Expansion Project

2017: Fluor completes FEED scope for the Ona Mining Expansion Project

In 2017, Fluor completed three front-end engineering and design (FEED) scopes for The Mosaic Company's Ona Mining Expansion Project. Utilizing our phosphate fertilizer project execution capabilities, Fluor completed trade-off studies, identified bottlenecks, performed onsite equipment capability assessments and developed a high-value process design. Based on successful completion of FEED work, Fluor was awarded the construction management scope.
2018
Fluor provides engineering and project management services for major bauxite mine in Guinea

2018: Fluor provides engineering and project management services for major bauxite mine in Guinea

Fluor is providing engineering and project management consultancy services for a major bauxite mine in the Boké region of Guinea. Fluor will manage part of the development of the bauxite mine, a dedicated export terminal in Port Kamsar and rail and other infrastructure upgrades. Fluor is also providing project management services for three major marine; rail & bridges; and material handling and infrastructure packages.
2018
Fluor awarded engineering, procurement and construction of Quellaveco Open Pit Copper Mine project
&w=3840&q=75)
2018: Fluor awarded engineering, procurement and construction of Quellaveco Open Pit Copper Mine project
&w=3840&q=75)
In 2018, Fluor was awarded the engineering, procurement and construction of the Quellaveco Open Pit Copper Mine project in Peru. Fluor has been responsible for the project's early site infrastructure development since 2014. The mine will produce 300,000 tonnes of copper per year.
2019
Fluor provides construction and project management for BHP South Flank iron ore project

2019: Fluor provides construction and project management for BHP South Flank iron ore project

Fluor was selected by BHP to provide construction and project management services for its South Flank iron ore project in the Pilbara region, Western Australia. South Flank will be the largest iron ore processing facility ever built in Western Australia.
2020s
2020 and beyond.
2020
Fluor completes Rhyolite Ridge Definitive Feasibility Study

2020: Fluor completes Rhyolite Ridge Definitive Feasibility Study

Fluor was selected by ioneer to perform the Definitive Feasibility Study (DFS) and subsequent engineering, procurement and construction management (EPCM) services as the project progresses for its Rhyolite Ridge Lithium-Boron Project in Esmeralda County, Nevada. Completed in April 2020, the DFS validates Rhyolite Ridge as a world-class resource with significant value creation potential due to its low-cost, large-scale operation and long mine life. The mine was expected to have a life of 26 years with the opportunity to extend and expand.