Pipelines Timeline
Building a Better World for More Than a Century
Fluor has designed and built onshore and subsea pipeline projects for more than 100 years. Since entering the hydrocarbon transportation industry in 1915, Fluor has executed complex pipeline projects on six continents. Fluor has installed more than 200,000 miles of onshore pipeline and designed some of the world's largest and longest offshore pipelines.
Whether designing pipelines to cross the severe terrain of the Andes Mountains or to withstand harsh Arctic conditions, Fluor has set the industry standard for pipeline engineering and construction.
1910s‑30s
Fluor awarded first contract in the hydrocarbon transportation industry to construct pipelines and compressor stations.
1915
Fluor enters the hydrocarbon transportation business
&w=3840&q=75)
1915: Fluor enters the hydrocarbon transportation business
&w=3840&q=75)
In 1915, Fluor received a significant contract to build a compressor station for the Industrial Fuel Supply Company, helping Fluor to later win other contracts from the oil and gas industry.
1915
Cross-country petroleum pipeline built
&w=3840&q=75)
1915: Cross-country petroleum pipeline built
&w=3840&q=75)
Williams Brothers Engineering Company, a Fluor subsidiary, built their first cross-country petroleum pipeline in 1915.
1930
Fluor expands to construct compressor stations on a pipeline between Texas and Indiana

1930: Fluor expands to construct compressor stations on a pipeline between Texas and Indiana

Significant oil finds in east Texas and booming gas operations throughout the midwest allowed Fluor to expand past California for the first time. Fluor was contracted by the Panhandle Eastern Pipeline Company for the construction of compressor stations on a pipeline between Panhandle, Texas and Indianapolis, Indiana. After completion of the project, Fluor opened an office in Kansas City to handle mid-continent contracts.
1940s
Fluor's pipeline experience extends to South America.
1942
Big Inch and Little Big Inch War Emergency Pipelines awarded

1942: Big Inch and Little Big Inch War Emergency Pipelines awarded

Williams Brothers was named the principal contractor to construct two War Emergency Pipelines. The pipelines connected the East Texas oil fields to New Jersey ports. First oil arrived at port in 1944.
1944
Venezuelan pipeline construction underway

1944: Venezuelan pipeline construction underway

Williams Brothers constructed a pipeline in Venezuela. It was the company's first international project. The expansion was later followed by subsequent work in South America.
1947
Construction begins on the Trans-Arabian Pipeline
&w=3840&q=75)
1947: Construction begins on the Trans-Arabian Pipeline
&w=3840&q=75)
The Trans-Arabian Pipeline (Tapline) was a significant industrial project bolstering the global petroleum trade. Fluor assisted Saudi Aramco with the construction of the Abqaiq pump station and power plant. In addition, Williams Brothers built a section of the main pipeline and the Sidon Terminal.
1947
Pipeline experience in South America expands with the construction of a Bolivian pipeline

1947: Pipeline experience in South America expands with the construction of a Bolivian pipeline

The 370-mile Bolivian pipeline contract was signed in 1947. This project continued to bolster the Williams Brothers' work in South America.
1950s
Fluor assists in building the Middle East's significant cross-country pipeline.
1950
First oil flows through Tapline
&w=3840&q=75)
1950: First oil flows through Tapline
&w=3840&q=75)
In 1950, the Tapline pipeline was completed. The Tapline stretched across Saudi Arabia, Jordan, Syria and Lebanon. This was a significant project that increased the global petroleum trade.
1953
Equitable Gas Company purchase necessitates interstate pipeline in the Eastern United States

1953: Equitable Gas Company purchase necessitates interstate pipeline in the Eastern United States

Fluor provided the engineering for the Equitable Gas Company compressor stations. Equitable Gas Company bought out Philadelphia Company holdings of gas fields in Pennsylvania, Kentucky, and West Virginia in 1947, necessitating an interstate pipeline system.
1955
First pipelines to serve oilfields in Western Canada under construction

1955: First pipelines to serve oilfields in Western Canada under construction

Williams Brothers constructed 350 miles of the 1,115-mile Interprovincial Pipeline. The Interprovincial Pipeline was the first to serve oilfields in Western Canada.
1960s
Fluor enters the offshore, subsea pipeline business.
1963
Pipelines from shoreline tanks lead to the Ulsan Refinery

1963: Pipelines from shoreline tanks lead to the Ulsan Refinery

The Korean Oil Cooperation hired Fluor to construct the grassroots Ulsan Refinery. The Korean company laid cross country pipelines between the refinery and the crude terminal area, a distance of nearly 3 miles. The refinery supplied demands for gasoline, light and heavy oils and other petroleum by-products.
1968
Fluor acquires fastest method for laying offshore pipelines with the acquisition of Aquatic Contractors
&w=3840&q=75)
1968: Fluor acquires fastest method for laying offshore pipelines with the acquisition of Aquatic Contractors
&w=3840&q=75)
In May 1968, Fluor announced the acquisition of Aquatic Contractors, a New Orleans-based company serving major oil companies with offshore oil production in the Gulf Coast. Aquatic's patented spool-pipe technique was the quickest method for laying offshore pipelines at the time. From the company's establishment in 1961 to acquisition, Aquatic's U-303 barge laid over six-million feet of spooled pipeline in the Gulf of Mexico.
1968
Fluor forms Fluor Ocean Services, Inc. and supports marine pipeline projects
&w=3840&q=75)
1968: Fluor forms Fluor Ocean Services, Inc. and supports marine pipeline projects
&w=3840&q=75)
Fluor announced the formation of Fluor Ocean Services, Inc., a new organization for offshore and ocean structures, facilities, vessels and systems. Fluor Ocean Services designed, procured and constructed marine pipelines, shore terminals and all related marine support facilities.
1970s
Fluor constructs the world's largest pipeline in Alaska.
1971
Fluor Ocean Services awarded contract for the installation of more than 37,000 feet of subsea pipeline

1971: Fluor Ocean Services awarded contract for the installation of more than 37,000 feet of subsea pipeline

Mobil Oil Corporation awarded Fluor Ocean Services (FOS) a contract for the installation of more than 37,000 feet of subsea pipeline in Singapore. Under terms of the contract, FOS laid six pipelines from Mobil's refinery at Jurong to a tank farm under construction on the island of Pesek. In addition, FOS laid three lines from Pesek to existing unloading facilities on the island of Ayer Chawan. The lines ranged from 14 inches to 30 inches in diameter.
1972
Fluor Ocean Services' reel barge lays one-millionth foot of submarine pipe

1972: Fluor Ocean Services' reel barge lays one-millionth foot of submarine pipe

On April 7, 1972, the RB-2 reel barge laid its one-millionth foot of submarine pipe. Pipelines ranged in diameter from two to twelve inches. Pipe was laid in water as deep as 350 feet - the deepest to date was laid in the Gulf of Mexico. The preceding barge, RB-1, laid in excess of 5 million feet of pipe during its operation.
1972
Trans-Andean Ecuadorian Pipeline passes through Andes at elevation of 13,331 feet
&w=3840&q=75)
1972: Trans-Andean Ecuadorian Pipeline passes through Andes at elevation of 13,331 feet
&w=3840&q=75)
The 313-mile, 20- to 26-inch crude pipeline began at Sacha, Ecuador and ended at Esmeraldas on the Ecuadorian coast. It included two crossings of the equator, more than a dozen major river crossings, virgin jungle, mountains, hills and deep valleys, plus one pass through the Andes at an elevation of 13,331 feet. The pipeline system had more than 57 miles of gathering lines, five pump stations and four pressure-reducing stations. In a number of sections along the right-of-way, rainfall exceeded 20 inches per month. An access road was built with log riprap topped with a thick layer of gravel. Williams Brothers Pipeline Company, the engineering portion of which was subsequently acquired by Fluor, provided construction services.
1976
Fluor lays 40 miles of submarine pipeline for Ardjuna project in Indonesia

1976: Fluor lays 40 miles of submarine pipeline for Ardjuna project in Indonesia

The Ardjuna field in the North Java Sea, Indonesia, was the site of the world's first completely offshore NGL recovery plant. Fluor designed and managed the project, which was capable of processing more than 230 MMCFD of natural gas. The ARCO and Pertamina plant included systems for gas gathering, gas compression, dehydration, chilldown and turbo-expansion, fractionation and LPG treating, spiking excess gas liquids back into the crude and product shipping facilities. The facility consists of two interconnected eight-pile platforms for the NGL process plant, one four-pile platform for crew quarters, four four-pile compressor station platforms, flare platforms and bridges, 40 miles of submarine pipeline and a single-point mooring systems for a 375,000 bbl capacity refrigerated storage barge.
1976
Fluor provides engineering management services for Australian Gas Light Company pipeline
&w=3840&q=75)
1976: Fluor provides engineering management services for Australian Gas Light Company pipeline
&w=3840&q=75)
Fluor provided engineering management services for an 834-mile, 34-inch natural gas pipeline extending from the Cooper Basin fields of South Australia to the Sydney region of New South Wales. Services provided included route selection including environmental studies; detailed design; project management; planning, scheduling and cost control; procurement of materials and equipment including expediting, vendor inspection and arranging transportation; construction management, supervision and inspection; and commissioning and startup.
1977
800-mile Trans-Alaska pipeline largest in the world

1977: 800-mile Trans-Alaska pipeline largest in the world

Fluor completed engineering, procurement and construction services for Alyeska's Trans-Alaska pipeline. Fluor's scope consisted of 12 pump stations and three refrigeration plants on rugged terrain; construction of one of the world’s largest marine terminals at Valdez; installation of control and power systems for 62 remotely operated gate valves; and meeting a schedule completion three years after construction startup, in subfreezing temperatures and blizzard-force winds. Fluor’s largest single task of the project was a 1,000-acre marine terminal in an environmentally sensitive area, carved out of a mountainside, at the Port of Valdez to receive the crude oil from the pipeline. Fluor designed the world’s largest floating berth at the time and the largest single prefabricated component of the pipeline.
1977
Pipeline from the Shedgum Gas Plant to Ju'aymah Terminal transports liquid natural gas byproducts to the coast

1977: Pipeline from the Shedgum Gas Plant to Ju'aymah Terminal transports liquid natural gas byproducts to the coast

Fluor provided engineering, procurement and construction management for the Shedgum Gas Plant, which was part of an overall Saudi Arabian gas program undertaken by Saudi Aramco to utilize natural gases previously considered waste product. In 1977, it was the largest gas-treating program ever undertaken. The Shedgum Gas Plant used Fluor’s proprietary process, Improved EconamineSM, to remove carbon dioxide, hydrogen sulfide and carbonyl sulfide from the gas. The main function of the plant was to remove sulfur from the natural gas and to partially fractionate the gas, splitting it into dry and liquid streams for shipment via pipeline to Ju’aymah. The dry gas, mostly methane, was used for fuel and feedstock, while the liquid stream of C2 and heavier hydrocarbons were further fractionated.
1979
Nigerian National Petroleum Corporation commissions totally automated pipeline system

1979: Nigerian National Petroleum Corporation commissions totally automated pipeline system

Fluor was commissioned for engineering, design, survey supervision, procurement and construction assistance of a 130-mile, 12-inch pipeline from Port Harcourt to Enugu and a 105-mile, 6-inch pipeline from Enugu to Makurdi. Scope of work also included pump stations, terminals, metering and support facilities necessary for operations and maintenance. The system was totally automated. The system was designed to transfer refined products from the Port Harcourt refinery to Aba and Enugu and from Enugu to Makurdi. Products delivered included regular and premium gasolines, diesel fuel, kerosene and aviation kerosene.
1979
Four 35,000 foot pipelines deliver crude from shore to offshore platforms

1979: Four 35,000 foot pipelines deliver crude from shore to offshore platforms

Fluor was responsible for the engineering and construction management of Saudi Aramco's Ju'aymah Terminal, one of the world's largest crude oil storage and loading facilities at the time. Pipelines that extended from shore to the offshore platforms included four 35,000-foot, 56-inch crude lines and two 24-inch bunkering lines. Twin 48-inch submarine crude lines and a single 18-inch bunkering line connected the offshore platforms to each of the single-point moorings.
1979
Southwest Wyoming pipeline first to use Skin Effect Current Tracing to maintain an elevated temperature

1979: Southwest Wyoming pipeline first to use Skin Effect Current Tracing to maintain an elevated temperature

The Carter Creek Sulfur Pipeline is a 6-inch, 20-mile liquid sulfur pipeline. The Southwest Wyoming pipeline was the first cross-country pipeline to use Skin Effect Current Tracing to maintain an elevated temperature. The gravity-flow pipeline was designed to transport 3,000 long tons of sulfur per day at an operating temperature of 280°F. Fluor conducted the feasibility study and preliminary cost estimate, project budget estimate and schedule, route selection and field location survey and mapping, detailed engineering, procurement, construction and construction management, field engineering, quality assurance during construction and commissioning and start-up assistance.
1980s
Fluor hones subsea pipeline technology and construction expertise around the globe.
1980
Turkish Petroleum Company implements enhanced oil recovery pilot program, including 50 miles of pipeline

1980: Turkish Petroleum Company implements enhanced oil recovery pilot program, including 50 miles of pipeline

Fluor's initial assignment for this enhanced oil recovery project included reservoir review and modeling, followed by engineering and economic analyses of several alternative enhanced recovery methods. As a result of the study, Turkish Petroleum Corporation began implementation of a large-scale pilot program of enhanced oil recovery by CO2 and water injection. The test involved production of 60 MMSCFD from a carbon dioxide field in a mountainous region of eastern Turkey. The gas was processed for removal of hydrogen sulfide and water at the production site and compressed and delivered to the test oil field via 50 miles of pipeline for injection. Due to the site’s remote location and the limited construction season, all major equipment was designed as pre-fabricated skid packages.
1980
More than 500 miles of main pipeline connects Saudi Arabia's four major gas plants with Ju'aymah terminal

1980: More than 500 miles of main pipeline connects Saudi Arabia's four major gas plants with Ju'aymah terminal

Saudi Aramco needed to construct the largest gas gathering and processing system undertaken at that time in the hydrocarbon industry, including the design and construction of the world’s largest offshore liquefied petroleum gas (LPG) loading terminal. In order to make the crude suitable for pipeline transmission, storage and export, approximately 500 cubic feet of natural gas had to be separated from every barrel of oil. Fluor’s offshore group engineered more than 500 miles of gas gathering pipelines to bring the associated gas from the gas oil separation plants to the gas plants. From there, pipelines then connected the gas plants to the major export terminal at Ju'aymah. In May 1980, the first ocean-going taker took on product at Ju'aymah.
1981
Gulf of Thailand pipeline is the longest submarine pipeline in the world to date
&w=3840&q=75)
1981: Gulf of Thailand pipeline is the longest submarine pipeline in the world to date
&w=3840&q=75)
Fluor acted as managing contractor for the construction of the Petroleum Authority of Thailand’s complete gas treatment and transmission system to transport natural gas from the Gulf of Thailand to onshore. The project consisted of 360 miles of offshore and onshore pipelines, a compressor station, offshore platforms, receiving terminals at Bangkok and Bang Pakong power stations, a distribution network and other equipment and facilities necessary to constitute a complete gas transmission system. The gas stream from UNOCAL's offshore field was transmitted 260 miles from the Gulf to Sattahip, Thailand through a 34-inch pipeline. At the time of its construction, it was the longest submarine pipeline in the world.
1982
Gas transported onshore via the NOGAT pipeline
&w=3840&q=75)
1982: Gas transported onshore via the NOGAT pipeline
&w=3840&q=75)
When Nederlandse Aardolie Maatschappij (NAM) opened a new sector of the Dutch North Sea, it undertook one of its more ambitious projects to date. The F3-FB offshore complex is owned and operated by NAM and located in the northern sector of the Dutch continental shelf in 148 feet of water. The offshore complex provides the final link in the 137-mile NOGAT pipeline. F3-FB produces 125-million-cubic-feet of gas and 24,000 barrels of oil per day. The oil and gas are separated offshore, allowing gas to be transported onshore via the NOGAT pipeline.
1982
Fluor's innovative pipeline hydraulics models optimize the design connecting Texaco's Highlander and Tartan A platforms
&w=3840&q=75)
1982: Fluor's innovative pipeline hydraulics models optimize the design connecting Texaco's Highlander and Tartan A platforms
&w=3840&q=75)
Texaco's Highlander Field development was a break-through in subsea technology that included universal trees and modular flowline connection concepts, a subsea slug catcher, retrievable pig launchers and receivers and diver-friendly designs for the 420-foot water depth. Subsea development of the marginal oil field included a 1,200-ton, 12-slot subsea template with remote wells, five pipelines, umbilicals, subsea slug catcher, riser systems and topside modifications. Fluor performed conceptual and detailed engineering, procurement and construction planning for the development of the Highlander Field oil and gas subsea production facilities.
1982
Ireland's longest gas pipeline transports gas from the Kinsale Field to Dublin

1982: Ireland's longest gas pipeline transports gas from the Kinsale Field to Dublin

Ireland's longest gas pipeline transported gas from the Kinsale Field, offshore the country's southern coast, to the city of Dublin. The reservoir, with reserves of some 1.3 trillion cubic feet of gas, lies in 310 feet of water 27 miles offshore. The gas flows through a submarine pipeline from two production platforms and comes ashore near Cork Harbor. Fluor supervised the entire project from design through commissioning. The 18-inch diameter line can carry 150 MMSCFD of gas from the reservoir at 1,000 pounds per square inch. Construction of the line required 18,000 39-foot lengths of pipe. After being corrosion-coated at Cork Harbor, it was trucked to the site and installed at the rate of a mile a day using a single-spread welding operation.
1982
Pipeline from the Kavala offshore field to the Prinos onshore processing plant complete
&w=3840&q=75)
1982: Pipeline from the Kavala offshore field to the Prinos onshore processing plant complete
&w=3840&q=75)
Fluor was responsible for design, engineering and construction management for two offshore drilling platforms and one production platform in the Prinos field, a drilling and processing platform in the Kavala Field and a pipeline to the onshore processing plant and onshore storage and shipping facilities. A 12-inches-in-diameter gas line piped sweet gas from the Kavala Field and sour gas from the Prinos Field to the onshore processing plant. An eight-inch pipeline separately channeled crude oil from Prinos Field after it was separated and dehydrated at the platform there.
1983
Gas from the Belier Field transferred through pipelines to S.I.R. refinery
&w=3840&q=75)
1983: Gas from the Belier Field transferred through pipelines to S.I.R. refinery
&w=3840&q=75)
Fluor was contracted by ESSO Exploration and Production Cote d'Ivoire, Inc. to construct drilling and production facilities in the Gulf of Guinea. As managing contractor, Fluor was responsible for engineering, procurement and construction management of the offshore drilling and production platform, as well as the pipeline and onshore reseparation and storage facilities. Oil and gas were separated on the platform before transfer to shore through a 10-inch-diameter coated offshore pipeline and a 10-inch buried onshore pipeline. The Abidjan project was located at a depth of approximately 200 feet and is designed to withstand 34-foot storm waves.
1984
Two main pipelines transport gas from production fields to Alrar, Algeria plant

1984: Two main pipelines transport gas from production fields to Alrar, Algeria plant

The Sonatrach Alrar Project, engineered and designed by Fluor, included extensive gas gathering and distribution systems. These pipeline systems, located in remote eastern Algeria, delivered feed gas to the Alrar Gas Treating Plant and distributed products from the plant to their desired destinations. Two main pipelines were included in the system. The Stah/Mereksen Pipeline, 60-kilometers long and 16-inches in diameter, transported gas from two producing fields to the Alrar plant. The pipeline was designed for a pressure of 96.7 bars at 71.1 degrees C. A 10-inch diameter, 45-kilometer condensate pipeline ran between Alrar and an existing pipeline at Ohanet. Designed for a pressure of approximately 69 bars, it could deliver up to 11,300 Nm3/day of hydrocarbon condensate.
1984
Ras Fanar Oil Field Development includes subsea pipelines
&w=3840&q=75)
1984: Ras Fanar Oil Field Development includes subsea pipelines
&w=3840&q=75)
A 12-month schedule, from start of design to delivery of the first shipment of oil ashore, presented a major challenge in completing the Ras Fanar Oil Field Development. Located on the Gulf of Suez, the Suez Oil Company project included two well-head platforms in approximately 100 feet of water, subsea pipelines and an onshore power plant, as well as crude sweetening and export facilities. Fluor completed its work well within schedule by negotiating a comprehensive, sole-source fabrication and construction contract.
1985
SECWA brings natural gas from Western Australia’s North-West Shelf to Perth
&w=3840&q=75)
1985: SECWA brings natural gas from Western Australia’s North-West Shelf to Perth
&w=3840&q=75)
Fluor assisted the State Energy Commission of Western Australia (SECWA) with the development of the Dampier to Perth Gas Pipeline. Fluor’s project management services included detailed design and engineering, procurement and logistic support, material inspection, construction management, quality assurance, training and commissioning.
The pipe was strung, welded, lowered in and back-filled. The pipes were made from high-strength carbon steel which allowed thinner than usual pipe walls and reduced overall tonnage and cost. The line was completed 80 days ahead of schedule.
1986
Statpipe Development Project exports gas from Norway to continental Europe

1986: Statpipe Development Project exports gas from Norway to continental Europe

Fluor provided project management services to Statoil for the Statpipe Development Project. The system carried both wet and dry gas through 530 miles of subsea pipeline. The northern part is a 180-mile long, 30-inch diameter wet gas line from Statfjord and block 34/10 to the Kårstø gas terminal on the west coast of Norway. At Kårstø, the dry gas is separated and exported through a 28-inch diameter line to a riser platform in the Sleipner area, a distance of 140 miles. Heimdal gas also connects to the same platform by a 96-mile long, 36-inch diameter line. From this platform, another 36-inch line carries dry gas 118 miles to a second riser platform at Ekofisk. Gas is then exported to continental Europe.
1987
Fluor completes construction for 46-mile Strategic Petroleum Reserve pipeline
&w=3840&q=75)
1987: Fluor completes construction for 46-mile Strategic Petroleum Reserve pipeline
&w=3840&q=75)
Fluor performed design, procurement support and construction services on a 46-mile, 40-inch diameter Strategic Petroleum Reserve pipeline that follows the Texas coast from Bryan Mound to an ARCO terminal in Texas City. The pipeline route was 75 percent within the 100-year floodplain. Design support included 13 drilled crossings, 137 foreign pipeline crossings, 17 highway/road crossings and 9 railroad crossings. Fluor handled most of the environmental and design permitting activities including a cultural resources survey, which found four archaeological sites. Three of the sites were avoided by directional drilling, while the other was fenced with the pipeline routed around it.
1987
Fluor designs three offshore platforms and five subsea pipelines offshore of Nigeria

1987: Fluor designs three offshore platforms and five subsea pipelines offshore of Nigeria

The Ashland project consisted of the engineering design of three offshore platforms and five subsea pipelines located in 130 feet of water offshore of Nigeria. Fluor was responsible for the design of three jackets, piping, decks, production facilities, flare bridges, flare tripods and 13 miles of subsea pipelines. The Mimbo, Bogi and Ukpam production facilities were designed for 16,500 BOPD, 7,500 BOPD and 9,000 BOPD, respectively.
1987
Product pipeline runs from Karachi to Multan

1987: Product pipeline runs from Karachi to Multan

This product pipeline system from Karachi to Multan included 533 miles of 16-inch pipeline, an 11-mile, 20-inch transfer line from a products terminal, 8.1 miles of 8-inch spur lines from local refineries, a 360,000-bbl initiating tank farm (with provision for later expansion to 960,000 bbls), products metering facilities and two pump stations. The pipeline ran parallel to the Indus River for roughly 400 miles. Other portions of the pipeline ran through mountains, deserts and flooded areas. The design of the communications facilities for the pipeline system included 17 microwave sites, a complete mobile radio system, automatic telephone exchanges and a block-valve radio control system.
1989
Aladja project pipelines deliver gas to the Aladja Steel Mill

1989: Aladja project pipelines deliver gas to the Aladja Steel Mill

The Aladja project for Nigerian National Petroleum Corporation consisted of 65 miles of 16-, 14-, 8- and 6-inch pipelines, eight gas compression and treatment stations and gas delivery facilities. The system was designed to gather approximately 55 MMSCFD of associated gas from eight oil flow stations at low pressure. The gas is compressed and treated to pipeline specifications and delivered through metering facilities to the Aladja Steel Mill. Twenty compressors totaling over 20,000 hp were installed at the eight compressor stations.
1990s
Fluor acquires Williams Brothers, a worldwide builder of pipelines, and moves hydrocarbon transportation office to Houston.
1991
Fluor completes engineering services for Wyoming-to-California gas pipeline system

1991: Fluor completes engineering services for Wyoming-to-California gas pipeline system

Kern River Gas Transmission Company awarded Fluor a contract to supply engineering services for a mainline compressor, field gathering stations and meter stations on the Wyoming-to-California gas pipeline system. The 700-million SCFD natural gas pipeline system ran from Opal, Wyoming, to Daggett, California, where it interconnected with the Mojave 42-inch pipeline system for delivery of Midwest and Canadian gas to consumers in Kern County, California. The system consisted of 688 miles of 36-inch pipeline, three compressor stations involving four 12,600-hp Solar Mars-driven centrifugal compressors, two gathering stations and twelve meter stations. Fluor's scope of work included detailed engineering design, project management and assistance with material procurement.
1992
Argentina and Chile team for Trans-Andean Oil Pipeline construction

1992: Argentina and Chile team for Trans-Andean Oil Pipeline construction

Fluor provided conceptual studies, route selection and design and construction consulting services to Yacimientos Petroliferos Fiscales, S.A. (YPF) and Empresa Nacional del Petróleo, Chile (ENAP) for the 265-mile Trans-Andean oil pipeline through Argentina and Chile. Argentina and Chile, with a history of political differences, teamed together for their mutual benefit on the development of the pipeline across the Andes. The 16-inch pipeline transported oil from the Neuquen basin, Argentina’s largest oil field, to Chile’s port of Concepcion where it was refined or exported. The pipeline, completed in 1992, was built over the rugged terrain of the southern Andes, and was operational at half capacity 15 months into the project, allowing Argentina to begin exporting and producing revenues earlier and providing Chile a steady supply of oil at slightly more competitive prices.
1992
Kutubu Petroleum Development Project includes over 160 miles of pipeline
&w=3840&q=75)
1992: Kutubu Petroleum Development Project includes over 160 miles of pipeline
&w=3840&q=75)
The Kutubu Petroleum Development Project - Export System was a development of the South Pacific Chevron Company in Papua New Guinea. Fluor performed engineering, procurement, project management and construction management. Fluor’s scope of services was to provide management, field supervision, survey and contract and procurement administration services as the client’s representative for the installation of over 160 miles of 20-inch O.D. pipeline for crude oil, onshore and offshore and a marine tanker loading terminal in the Gulf of Papua. Located in a remote and undeveloped area, the project required all infrastructure, including docks, camps, communication systems, medical facilities and other facilities. The system, completed in 1992, was designed for a capacity of 150,000 BPD.
1993
Empire State Pipeline carries 460 million CFD of natural gas
&w=3840&q=75)
1993: Empire State Pipeline carries 460 million CFD of natural gas
&w=3840&q=75)
ANR Pipeline, a subsidiary of Coastal Corporation, selected Fluor for inspection, project management and construction management of a 156-mile 24-inch natural gas pipeline that runs from the Canadian border west of Buffalo to a point north of Syracuse, New York. The Empire State Pipeline, which carried 460 million CFD of natural gas, included major directional drills of both channels of the Niagara River: of the Tonawanda channel, a 4,600 foot pipeline drill set the world record for length per diameter; of the Chippewa channel, a 3,800 foot drill. Another major drill was for the Erie Canal. The pipeline contained three metering and delivery stations, and it transported natural gas to provide fuel for electric utilities and cogeneration plants.
1993
Pipeline route crosses the environmentally sensitive Mojave Desert

1993: Pipeline route crosses the environmentally sensitive Mojave Desert

The Mojave Pipeline Operating Company contracted with Fluor for the pipeline from Topock, Arizona to Bakersfield, California. The pipeline was 386 miles long, with a 30- to 42-inch mainline and capacity of 1100 million cubic feet per day. Approximately 30 plant and animal species listed as "endangered" or "threatened" had potential to be encountered along the route. Environmental awareness training was provided to more than 1,500 construction workers. In 1991, the project was completed on time and under budget, with no exceedances of federally imposed environmental limits and no lost time due to environmental constraints.
1995
Fluor is responsible for the engineering design of Prudhoe Bay Field pipelines
&w=3840&q=75)
1995: Fluor is responsible for the engineering design of Prudhoe Bay Field pipelines
&w=3840&q=75)
Since 1981, Fluor was responsible for the engineering design of all pipelines and associated systems in the Western Operating Area of the Prudhoe Bay Field. Responsibilities included planning, engineering, procurement and field engineering support during construction in this environmentally sensitive area. The production lines (3-inch to 24-inch), waterflood lines (6-inch) and high-pressure miscible injectant gas line (4-inch to 12-inch) were designed with particular emphasis on protection of the tundra and permafrost. Design services included pipe stress analyses, pipe support design, pipe saddle and anchor design and gravel road and pad design. Construction management support for the installation of gravel pads, related access roads and the construction of a major bridge structure across the Kuparuk River were provided.
1996
Ulsan, Korea pipeline system reaches capacity of 58,000 barrels-per-hour
&w=3840&q=75)
1996: Ulsan, Korea pipeline system reaches capacity of 58,000 barrels-per-hour
&w=3840&q=75)
Yukong Limited, Korea’s largest refiner of petroleum products, contracted with Fluor to increase its crude import capacity. Fluor performed overall project management, detailed pipeline design, management of the Single-Point Mooring (SPM) / Pipeline End Manifold (PLEM) design, technical input for procurement and construction management on the submarine pipeline. The 42-inch-diameter pipeline, 4.5 kilometers in length, was installed to cross a shipping fairway, a 2-meter-diameter sewer outfall, traverse about one kilometer of rocky shore and 0.5 kilometer onshore to end at the booster station. The SPM buoy and pipeline accommodate tankers up to 325,000 deadweight tons. The pipeline system’s capacity is about 58,000 barrels-per-hour, which enables tankers to unload in about 36 hours.
1999
Trinidad's first offshore gas production piped to shore
&w=3840&q=75)
1999: Trinidad's first offshore gas production piped to shore
&w=3840&q=75)
The scope of facilities for the project included two offshore drilling and production platforms in 300 feet of water; 40-inch and 14-inch submarine gas and condensate pipelines running 62 miles to shore; a 36-inch, 50-mile-long, cross-country gas pipeline; and a 40,000 BBL/day condensate stabilization plant. Fluor performed project management, engineering, procurement and construction management services for Amoco Trinidad.
1999
ARCO Oriente Villano Oil Pipeline cited as an outstanding success by the Ecuadorian Government
&w=3840&q=75)
1999: ARCO Oriente Villano Oil Pipeline cited as an outstanding success by the Ecuadorian Government
&w=3840&q=75)
Fluor provided engineering, procurement, survey, construction and maintenance services to ARCO/AGIP for the development of the Villano field in a virgin Ecuadorian rain forest. The project involved production facilities and an export pipeline for 30,000 bpd crude oil development. The facilities included: well-site facilities; central processing facilities; electrical power generation facilities; a 40-kilometer, 12-inch flow line; a 40-kilometer power transmission line; 130-kilometers of an 16-inch oil export pipeline; pump stations; and a produced water handling and injection system. This project received ARCO's Environmental Achievement Award and was cited as an outstanding success by the Ecuadorian Government. Fluor helped the client save $50 million by using an innovative monorail system to transport the pipe along the fragile right-of-way. This "invisible pipeline" was constructed on a 3-meter right-of-way.
1999
Offshore pipelines complete Baltic Sea's first single point mooring terminal

1999: Offshore pipelines complete Baltic Sea's first single point mooring terminal

Fluor was the managing contractor for the ORLEN Lietuva (formerly Mažeikių Nafta) Butinge Oil Terminal. The Mazeikiu NAFTA facilities at Butinge, Lithuania, handled an annual throughput of 8 million tons of crude oil in the exporting mode and 5 to 6 million tons in the import mode. Facilities included a 36-inch, 7.5 km offshore pipeline; 22-inch pipeline to oil tankage; three 50,000-cubic-meter oil tanks; pump stations; and a single-point mooring terminal. A 22-inch crude oil pipeline transports crude between the refinery itself and the tank storage facilities nearby. A pipeline also connected to the Duzbai pipeline from Russia by means of a refinery bypass line. Fluor completed the project under budget and ahead of schedule, while reaching 2.5 million safe work hours.
1999
Atacama Pipeline crosses severe terrain
1999: Atacama Pipeline crosses severe terrain
The pipeline is part of an integrated energy project to provide natural gas as fuel for a power generating plant in Chile. The pipeline is 585 miles of 20-inch natural gas pipeline, plus 62 miles of 12-inch pipeline, from Northern Argentina to the West Coast of Northern Chile. Fluor provided the project engineering, procurement and construction management. CMS Gas Transmission and Storage Company, an affiliate of CMS Energy, is a major member of the consortium of U.S., Chilean and Argentine companies who undertook the project. The pipeline crosses tropical rain forest in Argentina, transverses severe mountain terrain, crosses the Andes Mountains at an elevation of 16,500 feet and crosses the Atacama Desert, the driest desert in the world, in northern Chile.
2000s
Fluor constructs critical onshore pipelines globally.
2001
Millennium Pipeline connects U.S. and Canadian gas sources and delivers gas across New York

2001: Millennium Pipeline connects U.S. and Canadian gas sources and delivers gas across New York

Fluor was selected to provide engineering, inspection and procurement services that included design, survey, mapping, field engineering, material handling and right-of-way management. The pipeline was to deliver natural gas from U.S. and Canadian sources to markets across the southern tier of New York State and the New York City metropolitan area. The pipeline diameter is 36 inches for the first 385 miles and 24 inches for 45 miles. Designed to 1440 psig for the 36-inch portion and to 1000 psig for the 24-inch portion, using X-70 grade pipe, the line includes metering and regulating stations, remote actuated valves, and a 2-mile crossing of the Hudson River. Millennium was a consortium that included Columbia Gas Transmission, TransCanada, Westcoast Energy and MCN Energy Group.
2002
CPC Crude Oil Pipeline System initial phase construction complete

2002: CPC Crude Oil Pipeline System initial phase construction complete

The $3.2 billion Caspian Pipeline Consortium Crude Oil Pipeline System stretches 1056-mile pipeline from Tengiz, Kazakhstan to a deep-water marine terminal on the Black Sea at Novorossiysk, Russia. During the first of five construction phases on the CPC Pipeline, the initial construction phase included 929 miles of pipe. Phase 1 involved refurbishing a 468-mile segment of pipeline; constructing 460 miles of 40- and 42-inch diameter pipeline and two pump stations; and refurbishing/upgrading three pump stations. The route crossed several hundred rivers and canals, including the 1 mile-wide Volga River. The pipeline became operational in October 2001, with completion of the initial phase construction in October 2002.
2003
Fluor constructs 1,000-mile pipeline from Chad to Cameroon
&w=3840&q=75)
2003: Fluor constructs 1,000-mile pipeline from Chad to Cameroon
&w=3840&q=75)
Fluor worked with ExxonMobil as part of an integrated management team to implement a successful strategy for this complex project, which was supported by the governments of Chad and Cameroon. Fluor constructed a 30-inch, 1,000-mile pipeline to transport Chad's oil across international boundaries to the west coast of Cameroon. The project met rigorous project requirements as set by the World Bank and ExxonMobil.
2006
Pipelines connect existing natural gas pipelines systems in Tamaulipas to Altamira's LNG Terminal for export

2006: Pipelines connect existing natural gas pipelines systems in Tamaulipas to Altamira's LNG Terminal for export

Terminal de LNG de Altamira was the first energy infrastructure project of its kind in Latin America. The project includes two 150,000 cubic meter full-containment tanks for LNG storage, LNG re-gasification facilities and short pipelines to connect to the existing natural gas pipelines systems in Tamaulipas. The completed facility receives shipments of LNG, gasifies the LNG and then places it into the natural gas pipelines, helping to increase the amount of natural gas available to Mexico.
2008
BUD Natural Gas Pipeline increases gas capacity by 2 million standard cubic feet per day
&w=3840&q=75)
2008: BUD Natural Gas Pipeline increases gas capacity by 2 million standard cubic feet per day
&w=3840&q=75)
Fluor provided preliminary and detailed engineering and design, procurement assistance and construction management on the new pipeline and related onshore gas and liquid receiving facilities for the National Gas Company (NGC) of Trinidad & Tobago. The project consisted of 65 kilometers of offshore 36-inch gas pipeline, starting at the foot of a riser on the Cassia B platform belonging to BP Trinidad and Tobago. New onshore gas/liquid receiving facilities, including an accumulator station, were to be built adjacent to an existing 30-inch pipeline facility at Abyssinia. The pipeline and new facility increased NGC’s gas capacity by 2 million standard cubic feet per day.
2010s
Fluor continues to set the industry standard for pipeline engineering and construction.
2014
Pipelines can transport the Strategic Petroleum Reserve's crude from underground caverns to supply the entire U.S. in the event of a supply chain disruption

2014: Pipelines can transport the Strategic Petroleum Reserve's crude from underground caverns to supply the entire U.S. in the event of a supply chain disruption

Located along the Gulf of Mexico, the Strategic Petroleum Reserve is the world's largest supply of emergency crude oil. Established after the 1973-74 oil embargo, the SPR has the capacity to store more than 700 million barrels of sour and sweet crude oil and maintains a minimum of 500 million barrels in reserves. This is estimated to be a 90-day supply for the entire U.S. in the event of a disruption in the supply chain. Crude oil has been withdrawn from the SPR three times, most recently in 2014 to verify how new pipelines and other infrastructure might affect the government's ability to transport the crude out of the underground caverns.
2014
Gladstone 270-mile gas pipeline part of landmark clean-energy project

2014: Gladstone 270-mile gas pipeline part of landmark clean-energy project

Fluor was awarded an engineering, procurement and construction (EPC) contract by Santos Ltd in January 2011 for its Gladstone Liquefied Natural Gas (GLNG) project in Queensland, Australia. Fluor’s EPC contract included upstream facilities associated with the 7.8 million tonnes-per-year liquefied natural gas project that will extract and liquefy gas from coal deposits for eventual export to Asia and other global markets. The LNG project involved development of coal seam gas production and processing facilities, onshore pipelines that include a 270-mile gas pipeline to Gladstone, and the LNG liquefaction plant at Gladstone. GLNG is a groundbreaking project that will use world-first technology to process coal seam gas into LNG. It represents a major investment in Queensland jobs and a cleaner energy source for the future.
2015
Fluor wins major contract for 250-mile Ohio to Michigan natural gas transmission pipeline

2015: Fluor wins major contract for 250-mile Ohio to Michigan natural gas transmission pipeline

Fluor was awarded a contract by NEXUS Gas Transmission, LLC, to provide engineering, procurement and constructionmanagement services for an approximately 250-mile natural gas transmission pipeline in Ohio and Michigan. The pipeline is capable of transporting 2 billion cubic-feet-per-day of gas. In addition to the 42-inch mainline pipeline, Fluor is designing and managing the construction of up to four compressor stations in Ohio, as well as four meter stations. The NEXUS Project is designed to meet growing demand for natural gas by distribution and end use markets in the Upper Midwest and Canada.
2016
Ramones II Sur Gas Pipelines transverse San Luis Potosi, Queretaro and Guanajuato, Mexico

2016: Ramones II Sur Gas Pipelines transverse San Luis Potosi, Queretaro and Guanajuato, Mexico

The pipeline project is a segment of the integrated Los Ramones transportation system, part of a strategy to supply central Mexico with natural gas imported from the United States. This project is the third phase of a transportation system that runs from the U.S.-Mexico border to Apaseo el Alto, Guanajuato. As a result of the increasing need for natural gas availability and distribution in different regions in Mexico, the project is expected to have a large impact on Mexico’s industry and economy. ICA Fluor will be responsible for the engineering, procurement, construction, testing, commissioning and start-up services of a 181-mile-long, 42-inch diameter pipeline with one compression station (for a total capacity of 1,420 MMCFD), located in the southern portion of the Los Ramones Phase II gas transportation system. The system is scheduled for completion in the second quarter of 2016.
2016
Fluor engineers and constructs pipeline that brings the Gavião Branco field into commercial operation

2016: Fluor engineers and constructs pipeline that brings the Gavião Branco field into commercial operation

A consortium including Fluor, Construcap CCPS Engenharia e Comércio S.A. (Construcap) and CFPS Engenharia e Projetos S.A. (CFPS), a joint venture of Fluor and Construcap, has met substantial completion on the Gavião Branco facility in the state of Maranhão, Brazil, turning it over to Parnaíba Gás Natural, Brazil's leading private gas exploration and production company. The consortium performed basic and detailed engineering, procurement, construction, commissioning and start-up of an 8.5 million-cubic-meters-per-day gas gathering system in the Gavião Branco field, as well as a 70-kilometer gas pipeline, under a demanding 12-month schedule. The project brings the Gavião Branco field into commercial operation, enables the tie-in of the Gavião Branco Sudeste field in the first quarter of 2016 and will provide the tie-in point for Gavião Caboclo and Gavião Branco Norte in the future.