&w=3840&q=75)
United U&O Project
Client: Jubail United Petrochemical Company (JUPC)
Location: Al Jubail, Saudi Arabia
Business Segment: Energy Solutions

Executive Summary
Fluor has a long-standing relationship with Sabic and its affiliate companies spanning more than 25 years. As the PMC contractor on the United Utilities & Offsites (U&O) project in Al Jubail, Saudi Arabia, we managed the lump sum turnkey (LSTK) contractors’ work for overall complex scope for the 1,000 KTA ethylene, 575 LTA EO/EG, and 150 KTS linear alpha olefins units, as well as performing the engineering, procurement and construction management (EPCm) for the U&O.
Other key units were an ethylene ground flare and an incinerator package. EPCm services were performed for U&O cooling water/seawater cooling system, steam/boiler feed water/condensate system, air systems, water systems, fuel systems, storage, fire water, wastewater treatment and flare and incineration systems.
Client's Challenge
The United Olefins Complex in Al Jubail, Saudi Arabia, was the first phase of a world-scale petrochemical complex for Jubail United Petrochemical Company, a wholly owned SABIC affiliate. Jubail United Petrochemical Company and Fluor formed an integrated project management team to manage the project.
Jubail United Petrochemical and Fluor initiated risk management programs, which were reviewed on a regular basis to ensure all risks were recognized. As a result of the risk reviews, action plans were developed and implemented to mitigate any identified risks.

Fluor's Solution
We were the program management contractor for the overall project, including LSTK process areas, and also performed as the EPCm contractor for the utilities and offsites. Engineering for master planning and for the U&O portions was performed in our Houston office, with portions of the detailed engineering work shared with our Manila, Philippines and Al Khobar offices.
Our responsibilities included safety leadership and implementation of the overall safety program; issuance of project specifications, procedures and standards; and standardization of equipment, instrumentation and building materials. Continuity among project areas, home offices and the job site was also a significant component of project management oversight.
We developed and implemented the turnover sequence and paths of construction, as well as the overall execution strategy and plan. Other tasks were performing the technical evaluation of the LSTK bids; overseeing the permitting, process safety and loss prevention for the overall plan; and managing the interfaces between the various LSTK contractors and the utilities and offsites project to enable continuity among the various work areas.
&w=3840&q=75)
The key units were the tanks for the following:
Monoethylene glycol (MEG)
Diethylene glycol (DEG)
Triethylene glycol (TEG)
Butene
Hexene
Octene
Decene
C12
C20+
Caustic (NaOH)
Hydrochloric acid (HCL)
The sheer scale of the United project helps to put its achievements in perspective:
Erected steel was equivalent to a 45-mile long line of Ford F150 trucks
Installed pipe was equivalent to a pipeline from Houston to Oklahoma City (about 450 miles)
Poured concrete was equivalent to a 56-mile long, two-lane highway
Moved soil was equivalent to twice the volume of the Great Pyramid of Egypt

Safety
The safety program met the challenges of a multilingual workforce of up to 14,000 people as well as the climate and other factors, breaking SABIC and Fluor safety records by achieving 50 million work hours without a lost-time accident.
Climate and Cooling
Sandstorms, temperatures approaching 49° C (120° F), and high relative humidity were planned for in order to have an effective safety program.
The seawater cooling tower was developed because the availability of seawater in the Jubail Canal system was limited. Developments in the Jubail industrial area typically rely on a large capacity of seawater to provide cooling on a “once-through” basis.
Diversity of Workforce
Key to the success of this project was the diverse workforce of nationals from 12 countries. The onsite workforce, peaking at 14,000, spoke 17 languages and 10 additional dialects. In addition, the United project benefited from a global execution platform: teams were working in Saudi Arabia, the United States, Manila, Japan and Germany. Multilingual and iconic safety signs were implemented to communicate with the diverse workforce.

Conclusion
The overall project (Pre-FEED, FEED & EPC) was completed in 42 months, and the utilities and offsites were completed in 38 months. Work sharing across Fluor offices in Houston, Texas, and Manila, Philippines, was a significant factor in completing the project in this record time.
The safety program met the challenges of a multilingual workforce of up to 14,000 people, as well as the climate and other factors, to break SABIC and Fluor safety records by achieving 50 million work hours without a lost-time accident.
The project began in 2001 and was completed in 2004.
