Fluor provided construction management, start-up, commissioning, and qualification services for the FMC Expansion Project. The new facility, Building 633, is a 337,000 square-foot space on MedImmune's existing campus.
The Fluor team brought cost and schedule certainty to the FMC Expansion Project through understanding and experience in the design and construction of similar facilities.
The final success of the FMC Expansion Project was measured by best-in-class construction safety; on target cost; and Government Post Approval Submittal (PAS) on schedule.
Other success factors included:
- Proactive project controls approach to monitor potential threats to the project cost and schedule
- Comprehensive turnover plan that was vetted early in project planning and allowed the team to completely install and transfer 243 systems in a six-month period
- Integrated construction and management teams completed all turnover activities safely, successfully, and on time