&w=3840&q=75)
LNG Canada Export Facility
Client: LNG Canada
Location: Kitimat, British Columbia, Canada
Business Segment: Energy Solutions
Industry: Energy Transition

Executive Summary
In October 2018, LNG Canada made a final investment decision to build its liquefied natural gas (LNG) export facility in Kitimat, British Columbia, Canada. The project represents the largest energy investment in Canadian history.
The LNG export facility will liquefy surplus Canadian natural gas so it can be safely exported to help meet global energy demands. Fluor's joint venture partnership with JGC Corporation is delivering multiple aspects of this project, including engineering, procurement, fabrication and delivery of modules, and construction of the project's infrastructure and utilities, marine structures and LNG storage tank.

Client's Challenge
LNG Canada is a joint venture comprising Shell (40%), PETRONAS (25%), PetroChina (15%), Mitsubishi Corporation (15%) and KOGAS (5%).
The project will have an initial capacity to produce 12.7 metric tonnes (14 million tons) of LNG per year with first shipment expected in 2025.

Fluor's Solution
The design of the facility meets some of the strictest regulatory standards in the world for safety, sustainability and environmental protection. In consultation with First Nations, work activities have been planned to minimize potential impacts to the local environment.
The project utilized a cost-effective modular construction approach. Large and complex modules were assembled by several existing fabrication yards and transported to the project site via water, minimizing construction congestion and disruptions in the community.
&w=3840&q=75)
In March 2022, the first major module, measuring 145 feet tall and weighing more than 5,000 tons, was received at the site. The final module arrived in July 2023, completing the module fabrication program. Overall, a total of 215 modules of varying sizes were received and set at the project site.
In the summer of 2024, train one of the project moved closer to completion with the final weld. This marked a pivotal moment in the construction of one of the largest energy projects in Canadian history. The final weld took 48 hours of continuous work from teams of welders working in shifts. More than 380 pipe welders had worked on the project since construction began in 2018.

The joint venture focused on hiring locally and throughout British Columbia and Canada. More than 4,500 jobs were created at the peak of construction, which required approximately 7,000 to 7,500 workers due to the shift work nature of employment.
Workforce development and training programs were developed for local community members, with a focus on developing positions for traditionally underrepresented individuals and groups. Contracting and procurement opportunities were also provided for First Nations and local businesses.

Conclusion
We have a long history of delivering successful projects in Canada, dating back to 1945, when we first broke ground on a refinery expansion in British Columbia.
Fluor and JGC began site activities for the LNG Canada project in 2018 and have since delivered multiple aspects of the LNG Canada megaproject, including engineering, procurement, fabrication and delivery of modules, as well as construction of the project's infrastructure and utilities, marine structures and LNG storage tank.
In February 2020, JGC Fluor and LNG Canada were jointly recognized by Shell with its Gold Hard Hat HSE award. The award recognized the project’s Design for Safe Construction program, which is focused on the elimination and significant reduction of hazards through design, providing an overall reduction to life-critical construction risk.

Project Gallery




