
JG Summit Petrochemical Complex Expansion
Client: JG Summit Petrochemical Corporation
Location: Batangas City, Philippines
Business Segment: Energy Solutions

Executive Summary
Fluor was awarded an engineering, procurement and construction management (EPCm) contract for the utilities, offsites and infrastructure scope of work for JG Summit's petrochemical complex expansion in Batangas City, Philippines.
The JG Summit Petrochemicals Group planned to increase ethylene production by 160,000 tons per year and propylene production by 110,000 tons per year. The Group would also add four new units to the facility: 2nd stage pygas hydrogenation unit, aromatics and butadiene extraction units and a new bimodal high-density polyethylene (HDPE) plant. The existing polypropylene (PP) plant would also expand its production capacity by 110,000 tons per year. The utilities and offsites project would therefore provide new and expanded utility systems to meet the demands of the complex, as well as upgrade the existing infrastructure.
Client's Challenge
JG Summit was the sole naphtha cracker operator in the Philippines and would continue to operate the facility during the construction phase. A six-week turnaround was scheduled, at which point all critical tie-in activities needed to be completed.
The challenge to the project was to complete construction, perform the tie-in works and have the system pre-commissioned and ready for full expanded plant operations after the turnaround.

Fluor's Solution
We executed EPCm for the complex's utilities, offsites and infrastructure from our Manila office, which is located only 60 km from the facility, allowing for greater interaction between engineering and construction. In 2017, Fluor completed the simplified front-end engineering and design work for the expanded utilities and offsites systems.
Additionally, our Manila office provided program management consulting services for the project, simplifying the interface process with the other EPC contractors.
In June 2019, the project team achieved 5 million work hours without a lost-time incident.

Conclusion
We executed the utilities, offsites and infrastructure scope for JG Summit’s petrochemical complex expansion. The project was planned to be completed in phases, with the cracker expansion, new 2nd stage pygas hydrogenation and new aromatics and butadiene extraction units completed in mid-2019, and with the polypropylene expansion and new HDPE facility completed the following year.
