The COOEC-Fluor fabrication yard delivered the Huizhou module on schedule, fabricating the 4,000-ton, four-deck topsides in less than 12 months. The team delivered the module with no follow-on work.
The project team optimized the fabrication method and onshore commissioning scope, which minimized the schedule-intensive offshore installation requirements.
The COOEC-Fluor team was also responsible for the close-out activities and sea fastening work.
Safety was at the forefront of all activities. The team achieved 1.5 million work hours without a lost-time incident.