Savannah River Plutonium Processing Facility (SRPPF)

Savannah River Plutonium Processing Facility (SRPPF)

Client: U.S. Department of Energy (DOE) National Nuclear Security Administration (NNSA)

Location: Aiken, SC, U.S.


Business Segment: Mission Solutions

Industry: Government

Map showing the location of Savannah River Plutonium Processing Facility (SRPPF)

Executive Summary


Savannah River Nuclear Solutions, LLC (SRNS), a Fluor-led partnership comprising Fluor and HII, is responsible for managing the Savannah River Plutonium Processing Facility (SRPPF), a major U.S. National Nuclear Security Administration (NNSA) initiative that will repurpose an unfinished facility at the Savannah River Site (SRS) to manufacture at least 50 plutonium pits per year (ppy) in support of the nation’s nuclear deterrent.

Client's Challenge


Under federal law and to meet national security requirements, the NNSA is implementing a two-site strategy to establish an enduring capability to produce at least 80 war reserve ppy, with SRS responsible for at least 50 and Los Alamos National Laboratory (LANL) responsible for at least 30.

To meet pit production requirements at SRS, NNSA is repurposing the unfinished Mixed Oxide Fuel Fabrication Facility as the SRPPF. The repurposing of the over 400,000 square foot, Hazard Category-2 facility requires extensive modifications and installation of manufacturing and support equipment directly associated with the pit production mission. The project also involves construction on more than 20 additional support facilities and temporary infrastructure for the construction workforce.

Fluor's Solution


Fluor-led SRNS has served as the management and operations (M&O) contractor at the SRS since 2008. SRNS is leveraging its operational history at the site with Fluor’s engineering and construction expertise to manage the accelerated conversion of the existing facility into the SRPPF.

SRNS has assembled a project team that includes staff from multiple national laboratories, including LANL, external engineering firms, and subcontractors. The team integrates technical expertise and project execution capabilities to advance construction and prepare for future operations.

In October 2026, SRPPF received approval to proceed with full-scale construction following the NNSA’s approval of Critical Decision (CD)-2/3, two months ahead of schedule. CD-2/3 approval is a major milestone in advancing the SRPPF project, marking the formal completion of the design phase and authorizing construction. When complete and operational, SRPPF is expected to employ a workforce of over 2,000 personnel.

Conclusion


In close collaboration with NNSA, Fluor-led SRNS is managing the project delivery of the Savannah River Plutonium Processing Facility at the Savannah River Site near Aiken, South Carolina. The construction of SRPPF is a top priority for the U.S. government as it will reestablish the nation’s capability to produce plutonium pits in support of sustainable nuclear deterrence.