Fluor provides procurement, project management and construction management services. Phase 1 of the project comprises a 450,000 t/a state-of-the-art board machine, auxiliary facilities, including power plant, fresh water treatment, effluent treatment and necessary infrastructure. The project employed 5,500 construction workers at peak.
In 2016, the National Safety Council recognized the project with the Million Work Hours Award for exceptional safety performance.