Client
Confidential
Location
Texas, U.S.

Texas Cogeneration Facility

Fluor provided turnkey EPC and start-up services for this 440MW combined- cycle cogeneration facility.

  • The project was completed three months ahead of the contract schedule
  • 235MW of electricity and 1.1 million pounds per hour of steam are used to provide energy for the Client's chlor-alkali production plant
  • Two GE Frame 7FA combustion turbine generators, two Deltak HRSGs and a single ABB steam generator were installed onsite