Mariner East 2 Project
Client: Energy Transfer Partners
Location: Marcus Hook, PA, U.S.
Business Segment: Energy Solutions
Industry: Fuels

Executive Summary
Fluor provided procurement, commissioning, construction and construction management services for Energy Transfer Partners' Mariner East 2 project at the Marcus Hook Industrial Complex, a world-class terminal owned by Energy Transfer subsidiary Sunoco Partners Marketing & Terminals on the Delaware River in Pennsylvania. Upon completion of new terminal facilities to store, chill, process and distribute propane, butane and ethane for domestic use and export, Mariner East 2 was anticipated to provide up to an extra 275,000 barrels per day of natural gas liquids (NGLs) for distribution.
Client's Challenge
The Marcus Hook Industrial Complex includes terminal and storage assets and related commercial agreements. The facility can receive NGLs via marine vessel, pipeline, truck and rail and can deliver via marine vessel, pipeline and truck.
The Marcus Hook Industrial Complex served as an off-take outlet for the Mariner East 1 system. The Mariner East project transported NGLs from Western Pennsylvania, West Virginia and Eastern Ohio to destinations in Pennsylvania, including the Marcus Hook Industrial Complex. The project footprint covered 19 acres.
Source: Sunoco Logistics website

Fluor's Solution
We constructed new terminal facilities for the Mariner East 2 project at the Marcus Hook Industrial Complex. Upon completion, Mariner East 2 was anticipated to provide 275,000 barrels per day of NGLs for distribution to local, regional and international markets.
The Mariner East 2 project comprised the following major elements:
Four product storage tanks (by third party)
Refrigeration equipment
Dock-mounted load-out equipment and piping modules (by third party)
Dock rehabilitation
Substation (by third party)
Two incoming feeders from the new substation
New firewater supply and distribution system
In-plant pipe runs and supports
Incoming pipeline for NGL feedstock
Electrical and instrumentation
Cooling water tower
Flare system
Fluor, the client and contractors used our project-wide communication platform Fluor Site Connect℠ to access key information throughout the project site, contributing to a largely paperless jobsite.
More than 2,200 craft personnel supported the project representing Fluor, building trades and local unions. Our direct-hire craft peaked at 196 in November 2016, and our staff peaked at 143 in January 2017.
Our offices in Houston, Texas, Greenville, South Carolina and Manila, Philippines, supported the project.

Conclusion
We provided procurement, commissioning and construction services as part of an integrated solutions approach for Energy Transfer Partners’ Mariner East 2 project at the Marcus Hook Industrial Complex in Pennsylvania. Upon completion, Mariner East 2 was anticipated to provide 275,000 barrels per day of NGLs.