Brazos Electric began providing reliable electricity from the Jack County Unit 1 to cooperative members in 2005 and is Brazos Electric’s most reliable power plant in their fleet.
Fluor had an exemplary safety record with more than 900,000 hours worked without a lost-time accident, OSHA recordable incident or restricted workday case, while delivering the project three months ahead of the guaranteed commercial operation date.
As a result of Fluor’s outstanding performance on Unit 1, Brazos Electric felt confident when they awarded Fluor the Jack Unit 2 expansion project in 2008. Fluor will use a similar reference plant design for the new Unit 2 generating facility to shorten the schedule and minimize plant operating costs.