Executive Summary
Client's Challenge
Fluor's Solution
Conclusion
In 2004, Fluor, together with TASNEE, formed an integrated project management team that oversaw the entire Ethylene Cracker / PE complex, resulting in contract awards to a consortium of Linde / Samsung in July of 2005 for the cracker project and Tecnimont in January 2006 for the PE projects.  This trendsetting project management approach resulted in the ethylene cracker plant completed safely, ahead of schedule, and within budget in August 2008, HDPE in Nov 2008, and LDPE in Jan 2009.